When the Internal Requisition will get generate if I define
an OSP operation in sequence 30. 10 & 20 will be other than
OSP operations.
Answers were Sorted based on User's Feedback
Answer / shabbir
The purchase requisition (PR) gets generated for OSP and not
the internal requisition.
And it depends on the Requisition Creation Time
parameter in WIP Parameters 'Outside Processing' Tab.
1. At Job/Schedule Release - The PR gets generated
immediately after the Job or Schedule is released.
2. At Operation - The PR gets generated once the move
transaction reach the Queue of the OSP operation sequence.
3. Manual - PR need to be generated manually.
| Is This Answer Correct ? | 19 Yes | 0 No |
Answer / santhosh kumar gp
It all depends on how u set the Requisition Creation Time
parameter in WIP Parameters' Outside Processing Tab.
1. At Job/ Schedule Release
2. At Operation
3. Manual
| Is This Answer Correct ? | 16 Yes | 1 No |
What are the basic modules of Oracle Apps? Which are very popular
24 Answers Accenture, iGate, TCS, Textiles, Wipro,
What is an Organization Assignment?
How Many Inventory Org can be/are there
can any one help me to resolve this error "&SEGMENT refers an invalid output DESCRIPTION for system Items" when i query an job in the MAterial Requirements user interface
How do you ensure on and availability are daily base for min max planning?
What are phetom item? How are they user in business case?
hOW CAN We define bY Product in Discrete mfg
I want to create item in Inv org, why it is not taking,it is taking Master organisation,why give the reason.
If i want to map a organization structure, where i hv 1 operating unit that is looking after only purchasing and payables activities, whereas another operating unit is looking after OM as well as receivables. I hv one more warehouse or say plant, where i am manufacturing & despatching the goods. Wiil it be solved by setting up purchasing at one OU and OM at another OU. Do I need to perform any additional setups? Please Suggest.
Just now i created one organization then i setup wip parameters in discreate jobs i found only one status 'how to update/create other status?
What is yield point?
Work order-less Completions