What is the actual consumption of bindingwire Per MT for
multi-storied housing construction

Answers were Sorted based on User's Feedback



What is the actual consumption of bindingwire Per MT for multi-storied housing construction..

Answer / us rao

it varies from projet to project depending on kind of steel
especially on no of sets of stirrups secondary
reinforcement provided in designs.usally around 8 to 10 kgs.

Is This Answer Correct ?    4 Yes 1 No

What is the actual consumption of bindingwire Per MT for multi-storied housing construction..

Answer / n.munusamy

7 kg per MT

Is This Answer Correct ?    5 Yes 3 No

What is the actual consumption of bindingwire Per MT for multi-storied housing construction..

Answer / shailender kumar

as per cpwd specification 4.5kg/mt

Is This Answer Correct ?    3 Yes 2 No

What is the actual consumption of bindingwire Per MT for multi-storied housing construction..

Answer / g.krishnan

2% of total weight of steel.it varies from projet to
project .usally around 8 to 10 kgs.

Is This Answer Correct ?    2 Yes 1 No

What is the actual consumption of bindingwire Per MT for multi-storied housing construction..

Answer / sunil

2% of total steel, or 8kg

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Civil Engineering Interview Questions

how to check aggregate quantity in stock yard

1 Answers  


what radial pressure, the NP2 class rcc pipe can sustain?

0 Answers   DVC,


How to design a beam without any typical(tuff) calculation. Answer Only by using site practical knowledge?

1 Answers  


Why sea sand and desert sand are dont used for construction

1 Answers  


what is the material consumption of 1:2:4 by kilogram?

1 Answers  






As a proof of my analytical skills I was asked to give an example of a real life situation that i have solved analytically ? Can anybody give me a clue what kind of examples should be a suitable answer ?

0 Answers   Infosys,


what is mean by c32/40s concrete class

0 Answers  


How much quantity of steel will be used for commercial building consists of ground floor shops, first floor shops, second floor will be for offices and third floor will be office/banks. How many tons of steel is required to construct this building.

3 Answers   CRPF,


9. What have you done to improve or develop your knowledge / professional qualifications in the last year?

0 Answers  


cement quantity in 1 M3 pcc

2 Answers  


what is the procedure involved in preparing mix design of m15 grade as per IS-10262-1982

0 Answers  


for basic costing, how can we calculate how much amount of steel and cocrete will go in per sqft? and what are the thumbrules?

1 Answers   Symphony,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4452)
  • Electrical Engineering Interview Questions Electrical Engineering (16637)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)