For G+4 storied building having 76000 sft per each floor,
can you prepare schedule in such a way that structure
should be completed with in 41/2 months and finishing be
completed with in 51/2 months?
Answer / sanjeev kumar jain
Definately Yes. We shall require all the detailed drawings
& specifications of construction first of all. Now we shall
arrange the activities of construction in a bar chart
manner with overlapping activities. We will have to asses
the magnitude of the most time consuming activities and
thus allocate max resources to these. By continious mix &
match combinations of time & resources, we can certailly
work upon a schedule which is required subject to the
conditions that the level of resources as required in the
planning part are actually available and there is no
ambiguity in overall action plan.
| Is This Answer Correct ? | 7 Yes | 0 No |
how many cubic centimeter in one unit of sand?
what are the types of dams
What are the applications of the modulus of elasticity?
state and explain in Water absorption of brick
How many % we consider for lap for reinforcement for estimates
What is min thickness,min grade of conc & age of PQC ?
Define Finite element method (FEM)
where can i get the previous question papers for rrb section enginerr (civil)
in m25 concrete what is m.
State the type of roads and compare the advantages and disadvantages?
what is rigid pavement
what is the stirrups? and which condition it is used?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)