For G+4 storied building having 76000 sft per each floor,
can you prepare schedule in such a way that structure
should be completed with in 41/2 months and finishing be
completed with in 51/2 months?
Answer / sanjeev kumar jain
Definately Yes. We shall require all the detailed drawings
& specifications of construction first of all. Now we shall
arrange the activities of construction in a bar chart
manner with overlapping activities. We will have to asses
the magnitude of the most time consuming activities and
thus allocate max resources to these. By continious mix &
match combinations of time & resources, we can certailly
work upon a schedule which is required subject to the
conditions that the level of resources as required in the
planning part are actually available and there is no
ambiguity in overall action plan.
Is This Answer Correct ? | 7 Yes | 0 No |
how to distinguish TMT n Tor steel?
what is right & short method of measurement of slab&beam
How can I calculate the Compressive strength of cubes after 28 days of curing?Is there any formula or ration ?
What is the density of most of construction materials?
What is the weight of Plunger used in Vicat Apparatus used for testing of cement for knowing standard consistency.How many grams of cement is generally used for this test?
how many bags of cement are needed to make a cement mortar of 1:3
5 Answers ABC, DBL, DHFL Dewan Housing Finance Corporation, VV, WADAN,
how to nfind out the specific gravity of sand.aggregate,water please help...
Concrete could be defined as, (1)An artificial stone (2)Structural stone (3)Strong stone (4)Rock and Sand stone
Approximate weight of a modular brick?
Sir how to find cutting length for footing steel bars in the shape of "u"
How much pressure will be drop when we apply the P.R.V. In the upvc downtake for stilt 28?
What will be the crank length in an staircase is same like an slab?