For G+4 storied building having 76000 sft per each floor,
can you prepare schedule in such a way that structure
should be completed with in 41/2 months and finishing be
completed with in 51/2 months?
Answer Posted / sanjeev kumar jain
Definately Yes. We shall require all the detailed drawings
& specifications of construction first of all. Now we shall
arrange the activities of construction in a bar chart
manner with overlapping activities. We will have to asses
the magnitude of the most time consuming activities and
thus allocate max resources to these. By continious mix &
match combinations of time & resources, we can certailly
work upon a schedule which is required subject to the
conditions that the level of resources as required in the
planning part are actually available and there is no
ambiguity in overall action plan.
| Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
Describe Briefly The Various Methods Of Concrete Curing?
how many mason and labaur work for a 1 brass bricks plz let me know the calculate & how to made calculation for this and whats the formulas for this?
What the advantages and disadvantage of using 90mm and 100mm bricks for a wall of a house? Thanks for any input.
How many hours should traffic be not allowed after completing wbm road or bst.and min how many hours should road rollers be used.
how to calculate the steel in 500yard
How many cum of 9.5mm stone in 1 ton ?
Sir, Iam Applied in rrb for the posts of Junior Engineer.I want to know about the or question previews to study well.Pl send it to shukla_varun1985@yahoo.com.
How do you maintain water pressure?
in the earthquqke the profile of water on dam is parabolic or not
What is meaning of FREE STANDING STAIRCASE ?
Sir how to find cutting length for footing steel bars in the shape of "u"
Floor tile measurement? Wall to wall or skirting to skirting
why the profile of shell of natural draught cooling tower is hyperabolic.
What is the release of lien?
What is meaning of tlc