For G+4 storied building having 76000 sft per each floor,
can you prepare schedule in such a way that structure
should be completed with in 41/2 months and finishing be
completed with in 51/2 months?
Answer Posted / sanjeev kumar jain
Definately Yes. We shall require all the detailed drawings
& specifications of construction first of all. Now we shall
arrange the activities of construction in a bar chart
manner with overlapping activities. We will have to asses
the magnitude of the most time consuming activities and
thus allocate max resources to these. By continious mix &
match combinations of time & resources, we can certailly
work upon a schedule which is required subject to the
conditions that the level of resources as required in the
planning part are actually available and there is no
ambiguity in overall action plan.
| Is This Answer Correct ? | 7 Yes | 0 No |
Post New Answer View All Answers
Explain how you can turn off the display for dimension in CAD?
What Is the Thumb rule to calculate depth and dia of pile required to carry specified load on differeent soil
brickwork labour rate per cum ?
how to calculate the concrete mix m30 by volume
What are the causes of building collapse?
what r the precaution for high in atp tempareture,low in atp tempareture
RR masonry rate analysis
How to plan a project
how can calculate the compressive strength of concrete cylinder by water cement ratio ?
What is the substitute of Mastic Asphalt?
how to calculate quantity of bricks in circular manhole with examples.
What is the requirement for over all CG of DG from the foundation surface to absorb the vibration of heavy set.
Which brick is best for construction ,either fly ash or AAC BLOCKS
What Reinforcements Are Used In The Process Of Prestressing?
What do we mean by partial moment release ??