What is Time at Large?
Answer / er. abhijit sane
Time is at Large when the project is likely to extend
beyond its dead line. Time is at large when there are
events which adversly affect the execution of the works and
result in dealy.
The delays may be due to deficiencies on part of the
Contractor or Owner
| Is This Answer Correct ? | 5 Yes | 1 No |
How much kilogram of binding wire required for fabricate one Metric ton of reinforcing steel
A person feels comfort when downs a stair because of ––
How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/
Why the name is "partial safety factor" why not "safety factor"?
0 Answers Engineers India Limited,
what is the use of bottom reinforcement in Cantilever Beam?
1m=3.281feet in that what is .281 mm cm m or anyother
How to design 12*12*14 room having rrc slab ,coloum, beam,foundation?
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
How to calculate Cement in bags ,sand in sqft and aggregate in sqft for 1cum M25 grade concrete
How to find the requirement of cement and sand for the 1cum of rr masonry work
how many nails required in one sqm shuttering.
1 Answers BCL, Era Infra Engineering, KR Traders, Sai Foundations,
For fine aggregate which is most suitable River sand or crusher sand & why ?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)