Explain the laying procedure and laying depth of submarine
cables under sea?



Explain the laying procedure and laying depth of submarine cables under sea?..

Answer / abhinav

An underwater electric power cable which has a minimum
radius of curvature to which it can be bent without damage
and which can be suspended between underwater suspension
points in no greater than a predetermined length for a
desired service life is layed by first laying a flexible
steel rope along the desired underwater course and
adjusting the rope position and length so that there are no
curvatures thereof less than the minimum radius and no
lengths thereof greater than the predetermined length, and
then, the cable is layed alongside the rope so as to follow
the configuration of the rope.

burial depth can be 5 metres for 132 kv .

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

What is the permissable nutral current of three phase system as per IS standards?

0 Answers  


1.protection used in transformer ? 2.Why breather called breather ? 3.Working of conservator tank.? 4.Speaker of parliament ?

4 Answers   Power Grid,


why there is a 2 slits in three pin's earthing pin?

1 Answers  


How to select Main CB Rating for 220 KW Load?

3 Answers   Voltech,


why dc supply is not applied for step up or down in transformer

3 Answers  






Can we pass 11kv power in 1.1kV voltage grade cable.If not why?.

3 Answers  


what are all types of cross section in AC cables?

0 Answers  


Types of test in Switchgears, MCC, NGR and DB's how it should be procced. Can anyone give me the details here or email me to pasuvaraj.k@gmail.com

0 Answers  


How do performance buccholz relay testing in power transformer

1 Answers  


How to calculate the input cable rating for 10kva ups (3phase input and single phase output and also 3phase output, battery rating 65Ah)provide the formula also.thnx

0 Answers   Bhel,


What is the need of earthing transformer for delta side of a transformer. (Think of a line section between a star/delta transformer at a grid substation and delta/star transformer at a village. An earthing transformer is there at the delta side of the star/delta transformer at grid substation). As there are no ground reference there will not be fault current if a one phase is grounded. Further L-L phase will be sensed by the primary side of star/delta transformer as a L-G fault. So why an earthing transformer is required at delta side

0 Answers   CEB,


how to calculate the cable size in sqmm if load (kw) is given?

5 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)