Why bent up bars provided in R.C.C slab
Answers were Sorted based on User's Feedback
Answer / agha zafar
it is actually economization of material. normally, for
fixed ended beams positive (sagging) moments are present at
the mid span and negative (hogging) moments at the supports.
so bottom steel is required at the mid span and top steel
resists negative moments at the supports. a bent-up is
provided to take the steel on the top at supports as bottom
steel is not normally required at at the supports (only
nominal steel is sufficient). hope it'd help!
| Is This Answer Correct ? | 311 Yes | 19 No |
Answer / mustafa mohammed layeak
Bent up bars (Cranked bars) in slabs are provided to resist
the negative moment (Hogging BM) produced at supports
(beams).
| Is This Answer Correct ? | 132 Yes | 4 No |
Answer / rajnish kumar
to prevent negative bending moment at corner
| Is This Answer Correct ? | 3 Yes | 0 No |
Answer / ritesh
These are main reinforcement bent up at suitable angle generally 45degree ,
these are only provided with shear reinforcement.
| Is This Answer Correct ? | 13 Yes | 12 No |
Answer / aabid
bent up bar required slab because shear force develop in the corner side so this develop shear force stopped so need for bent up bar required.
| Is This Answer Correct ? | 2 Yes | 1 No |
Answer / nikita rajput
To resist negative hogging moment at ends n provision from torsional moment
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / abhishek sabale
To prevent from lifting at corner edges due to torsional moments.
| Is This Answer Correct ? | 6 Yes | 10 No |
From which end do you start deshuttering in a) cantilever portion b) simply supported portion
what is the maximum height of concrete casting.
How to check slab shuttering level.? Or check list for slab ?
how to consider the lap length of a bar in IS code and specify the code book name and clause& page number?
1 building project (work in progress) and following are sum detail about his project 1) Using local rebar grade 415 2) Total built up area- 60000 sq.ft 3) Floors to be constructed – 21 storey 4) Estimated requirement of Steel per sq. foot – 7KG/sq.ft 5) Concrete grade – M35 6) Rebars mainly required (sizes)- 16,20,25,32 & (8 mm for stirrups) Wanted to ask u if this person uses 500D…what are the benefits he will be getting? Whether his per Sq. foot consumption can b reduce? If yes den around how much?
What material should be used for casting the beam-column junction if beams and columns are of different grades?? For example concrete in beams and Columns is M20 and M25 respectively.
how much should we assume for the weight of foundation ??
08. 4 main points about check list for Shuttering works are––– 4 i) ii) iii) iv) 09. 4 main points about check list for Concreting works are––– 4 i) ii) iii) iv) 10. 4 main points about check list for Plaster works are––– 4 i) ii) iii) iv) 11. 4 main points about check list for Brick works are–– – 4 i) ii) iii) iv) 12. 3 main points about Project delaying factors are––– 3 i) ii) iii) 13. Write down 60-grade M.S. deformed bar specification. 3 14. 3000 psi concrete means: 1 15. 4 main points about methods of wastage control are–– – 4 i) ii) iii) iv) 16. 1 main point about reasons for your honesty is : 1 17. Water cement mixing in hopper less mixture machine is better than hopper mixture machine because: 1 18. 2 main points about your role during roof casting are–––– 2 i) ii) 19. a. The weight of 3333m deform bar of 24.5 mm dia is…… 1 b. The weight of 300 rft plain bar of dia 1 is……. 1 20. The types of slumps are––– 3 i) ii) iii) 21. 4 main points about the causes of cylinder failure are––– 2 i) ii) iii) iv) 22. Detection of a beam & a girder are–––– 2 i) ii) 23. Curing is needed for–––– 1 24. The types of slabs in respect of size & shape are––– 5 In respect of size: i) ii) In respect of Shape i) ii) iii) 25. The types of Column in respect of size & shape are–– – 9 In respect of size: i) ii) In respect of Shape: i) ii) iii) iv) v) vi) vii) 26. 3 field tests & 3 Laboratory tests of bricks are––– 6 Field tests: i) ii) iii) Lab test: i) ii) iii) 27. 2 field tests & 1 Laboratory tests of sand are––– 3 Field tests: i) ii) Lab test: i) 28. 1 field tests & 1 Laboratory tests of M.S rod are––– 2 Field tests: i) Lab test: i) 29. a. The % of water absorbs by brick chips: …………… 1 b. The % of water absorbs by Stone chips: …………… 1 30. In respect of design: 5 a. The % of strength gains by concrete in 28 days= b. The % of strength gains by concrete in 14 days= c. The % of strength gains by concrete in 07 days= d. The % of strength gains by concrete in 03 days= e. The % of strength gains by concrete in 28 days without curing =
HOW WE CALCULATE OR FIND OUT THE DEGREE OF FREEDOM IN A SIMLY SUPPORTED BEAM? IF THERE IS HINGE THEN HOW? & ALSO IN A PORTAL FRAME? PLEASE GIVE A EXAMPLE FOR EACH QUESTION.
Describe a time when you anticipated potential problems and developed Preventive measures
0 Answers Graham Construction,
what is the difference between np2 and np3 concrete mix
0 Answers Sri Matha Constructions,
Explain what is change order request?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)