Why bent up bars provided in R.C.C slab
Answer Posted / agha zafar
it is actually economization of material. normally, for
fixed ended beams positive (sagging) moments are present at
the mid span and negative (hogging) moments at the supports.
so bottom steel is required at the mid span and top steel
resists negative moments at the supports. a bent-up is
provided to take the steel on the top at supports as bottom
steel is not normally required at at the supports (only
nominal steel is sufficient). hope it'd help!
Is This Answer Correct ? | 311 Yes | 19 No |
Post New Answer View All Answers
load combinations how many types for staad design purpose?
How to calculate the cement and fine aggregate requirement for solid block masonry works in terms of Sqm. 1. 400x200x200mm 2. 400x200x100mm 3. 600x200x100mm 4. 600x200x200mm I need the answer for 1 Sqm of solid block works.
How to calculate unit weight of concrete for m40 grade.
WHAT WII BE THE WATER ABSORPTION POWER OF WOOD ?
residential projects,structural.
What are advancements in civil engineering?
Where will be the maximum bending moment in a TEE Beam?
can you mail me detailed procedure,entire syllabus and practice papers of mpsc civil engineering branch.I am in third year now
how to find ssm in foundation?
Reinforced concrete: suppose you are doing rough estimate for purchase of rebar for reinforced concrete slab for single stores residential building. You know total concrete volume will be 100 m3. How many tons rebar 6, 10 and 12mm will you require for the project?
I measured pcc work as 15.34 m cube , the ratio is 1:5:10 ,want to know the cement, sand and metal used for pcc measured as 15.34 m cube at this ratio.
What will you do if a portion of load bearing wall collapses under your supervision?
how to calibrate the RM 800
to minimize budget cost of building , what can i do
Why are pull-out tests performed for soil nails?