Why bent up bars provided in R.C.C slab
Answer Posted / agha zafar
it is actually economization of material. normally, for
fixed ended beams positive (sagging) moments are present at
the mid span and negative (hogging) moments at the supports.
so bottom steel is required at the mid span and top steel
resists negative moments at the supports. a bent-up is
provided to take the steel on the top at supports as bottom
steel is not normally required at at the supports (only
nominal steel is sufficient). hope it'd help!
| Is This Answer Correct ? | 311 Yes | 19 No |
Post New Answer View All Answers
Sometimes the side of concrete bridges is observed to turn black in color. What is the reason for this phenomenon?
What is thumb rule in quality and quantity estimation of a Residential building??
Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required
How many are the types of joints?
What are the advantages of building a dam on the river nile?
can any one explain bar bending schedule of bems and columns and slabs ??
What is alternate bid?
any book or article on pumped concrete.
What is critical path method (c.p.m)?
How we calculate the service time of buildings
Explain what is alternate bid?
What is geopolymer based concrete?
how do i remedy a foundatiom that the column bases was cast and aftet 28days crushing the conprehensive strength of the concrete fall below the specification 25N/mm2
what is the list of building construction equipment & teir output?
What is quantity of cement and sand required for 2000sqft of tiling?