Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


how can we calculate the cutting length of 10,12,16,20 and
so on iron bars for 45 digree and 90 digree bents plz tell
me if there is any formula or tabel to find it

Answers were Sorted based on User's Feedback



how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / 03265523

for example if any steel take 1.0 meter cutting length

density= weight / volume

density of steel is 7850kg/m3
volume of steel = areaX length=3.14xD2/4*1.0
weight of steel for 1m is= density X volume
= 3.14D2x1000*7850/1000*1000*1000
=D2/162 (square of D/162)
where D is the dia of bar in mm
for 45degrres =cutting length-1 * dia of bar* no of bends
for 90 degrees= cutting length-2 * dia of bar*no of bends

Is This Answer Correct ?    258 Yes 57 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / sumit

For 45 degree
Cut lenth is = Total lenth - 1*dia of bar* No. of bends

For 90 degree
Cut lenth is = Total lenth - 2*Dia pf bar* No.of.bends

For any civil enginering related question Contect me by
mail ID
skatiyar011@yahoo.in

Is This Answer Correct ?    74 Yes 20 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / bikash bhowmick

for calculation of cutting length deductions for 90 degree bend is......cutting length= total length- 2* dia of bar(upto 20) and 3*dia of bar when bar dia 25 and above......

Is This Answer Correct ?    43 Yes 11 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / dharvinder singh

it is not understanding that we have to deduct one dia for
both 45 degree & 90 degeree . their should be an other
formula

Is This Answer Correct ?    56 Yes 31 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / prabhu

The answer posted should some reference from any of IS code.
It has to be justified.
As i refered code IS 2502 BS 4466 the deductions followed are
0 for 45 bends
d<= 16 dia for 90 bends
2d>=20 dia for 90 bends

Is This Answer Correct ?    37 Yes 14 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / pranjal bokare

there is a formula for finding out the extra length
required for one bent. i.e. 0.42d where d is the effective
depth of the member.

Is This Answer Correct ?    18 Yes 10 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / abhay

The best way to find out the cutting length of bar:
1 Check dia of bend of bar given in specification.
2.follow the formula given in BS 8666:2005 ir IS 2502-1963

this is best
good luck!

Is This Answer Correct ?    12 Yes 4 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / arun

Total Length-2(Elongation)*Dia of Bar*No of Bend

Is This Answer Correct ?    5 Yes 1 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / muhammad abdullah

To calculate the bending Deduction formula given Below.

Bend Deduction = 1.25*Dia of Steel*No of Bend

Is This Answer Correct ?    13 Yes 11 No

how can we calculate the cutting length of 10,12,16,20 and so on iron bars for 45 digree and 90 di..

Answer / deepak

1)for 90 degree bend 3/4of D
D=depth of the structure

2) for 45 degree use pythagars theorm

Is This Answer Correct ?    12 Yes 11 No

Post New Answer

More Civil Engineering Interview Questions

what is westage % for steel, concrete,tiles,pains as per indian staderd code?

6 Answers   DLF, Engineering, Lodha, Tata Steel Limited,


is basic cost of the material includes tax?

0 Answers  


in BUILT UP AREA BASIS WHAT IS RATIO OF CONCRTE & STEEL RATIO MAY BE CONCIDER IN PER SQFT QTY

2 Answers   L&T,


Plese tell me about cranked beam (end hook lenth, crank angle, crank length). Thanks.

1 Answers  


What is GSB gradation

0 Answers  


How to take labor charges for construction of 1cum of concrete?

0 Answers  


Use of coping on terrace wall and in 4" wall is compulsory or not ?

0 Answers  


Define What is rigging?

0 Answers  


what is ment by surveying?

3 Answers   UltraTech,


how to calculate shuttering measurement of beam and slab

3 Answers   NCCL,


My daily concrete volume of M25 concrete is 1st day= 25 Cum 2nd Day = 45 Cum 3rd Day = 55 Cum 4th Day = 22 Cum 5th Day =72 Cum 7th Day = 49 Cum. What will be acceptance criteria of concrete considering as per is 456 cl.15 and table 11 (cl 16.1 and 16.3).

0 Answers   L&T,


in which code refer the change of reinforcement dia defer to drawing . i.e. 12mm dai into 16mm dia.

3 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)