The outputs of the Administrative Closure process include all of the following except: A. Project archives B. Project closure C. Lessons learned D. Formal acceptance
1011You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are performing earned value analysis, trend analysis, and performance reviews. Which of the following is true? A. This is performance measurement documentation, which is an input to the Contract Closeout process B. This is performance measurement documentation, which is an input to the Administrative Closure process C. These are performance reporting tools and techniques of the Administrative Closure process D. These are performance reporting tools and techniques of the Contract Closeout process
880You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.
1089Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.
1267Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating
973Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects
1028Contract documentation is an input to the Contract Closeout process. Contract documentation might include all of the following except: A. Supporting documents B. Contract changes C. Financial documents D. Procurement audit documents
1041Procurement audits review what? A. The procurement process from Procurement Planning through Contract Administration B. The contract administration process from Solicitation Planning through Contract Administration C. The procurement process from Procurement Planning through Contract Closeout D. The contract administration process from Solicitation Planning through Contract Closeout
956As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except: A. Personal integrity of others B. Project management process C. Personal integrity D. Product integrity
1061You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.
1027Integrity in the project management field is accomplished through all of the following except: A. Training to learn how to manage relationships with others from different cultures B. Adhering to an ethical code C. Applying established project management processes D. Following the Project Management Professional Code of Professional Conduct
1017You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.
1107You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors invites you to lunch. What is the most appropriate response? A. Thank them but let them know this could be a conflict of interest since you haven't made a decision about which vendor you're going to choose. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. You don't believe there is a conflict of interest or a personal integrity issue. D. Thank them and decline. You believe this could be a conflict of interest on the part of the vendor, and you don't want to encourage that behavior.
1005You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response? A. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. Immediately report your actions to the project sponsor so that your motives are not called into question after the fact. D. Thank them and decline. You know this could be considered an integrity issue on the part of the vendor.
1002You are a project manager working on contract with a company in a foreign country. At the project kick-off meeting, you are given an expensive-looking gift. The person who presented this to you said that it is customary in their country to give their business partners gifts. What is the most appropriate response? A. Thank them and decline. Explain that this is considered personal gain, which is unacceptable in your country. B. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. C. Thank them and decline. Explain that this is considered a conflict of interest, which is unacceptable in your country. D. Thank them and accept since you know that it would be considered offensive to decline the gift in their culture. Immediately report the acceptance of the gift to the appropriate parties at your company so that your actions are not called into question later.
1246Post New Project Management Questions
Which of the following is true regarding Administrative Closure? A. It occurs at the end of a project phase and at the end of the project. B. It occurs at the end of the project phase only. C. It occurs at the end of the project only. D. It is performed prior to Contract Closeout.
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true? A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process. B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process. C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process. D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.
You are the project manager for your company's annual Spring Fling. You've made all the plans and reserved the outdoor grounds for the appropriate day and time. You are now two days away from the big day, and the forecast is calling for light rain showers in the afternoon. You rented tents just in case this risk occurred. This is an example of which Risk Response Planning tool and technique? A. Passive acceptance B. Contingency planning C. Avoidance D. Transference
All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction
Your company. Kick That Ball Sports, has appointed you project manager for their new Cricket product line introduction. This is a national effort, and all the retail stores across the country need to have the new products on the shelves before the media advertising blitz begins. The product line involves three new products, some with multiple deliverables. The Scope Definition process is now complete. Which of the following is true? A. The WBS template, an output of the Scope Definition process, was used from the previous project to create the WBS for this project. The WBS encompasses the major deliverables for the project. B. The WBS template from the previous project, an output from the Scope Planning process, was used to create the WBS for this project. The WBS encompasses the major deliverables for the project. C. The WBS, an output of the Scope Planning process, has been created, and it encompasses the full scope of work for the project. D. The WBS, an output of the Scope Definition process, has been created, and it encompasses the full scope of work for the project.
You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response? A. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. Immediately report your actions to the project sponsor so that your motives are not called into question after the fact. D. Thank them and decline. You know this could be considered an integrity issue on the part of the vendor.
What type of organization experiences the least amount of stress during project closeout? A. Projectized B. Functional C. Weak matrix D. Strong matrix
Which of the following is true regarding the scope statement? A. It describes how to make changes to project scope. B. It describes project deliverables and serves as a baseline for future project decisions. C. It assesses the stability of the project scope and is a baseline for future project decisions. D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.
What are the framework activities and umbrella activities?
You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and how the information should be stored and filed is which of the following? A. Scope management plan B. Communications management plan C. Information distribution plan D. Project charter
What is the purpose of the project charter? A. To recognize and acknowledge the project sponsor B. To recognize and acknowledge the existence of the project and commit organizational resources to the project C. To acknowledge the existence of the project team, project manager, and project sponsor D. To describe the selection methods used to choose this project over its competitors
Lessons learned are used for all of the following except: A. To provide historical information that you can review during your next project B. To document employee performance C. To identify successes and failures on the project D. To record the causes of performance variances
You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time