Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Project Management Interview Questions
Questions Answers Views Company eMail

The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

1648

You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

1510

Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.

1066

All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT

1012

You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity

813

You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

1139

You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4

1167

If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following? A. The activity will take between 488 and 512 days. B. The activity will take between 464 and 536 days. C. The activity will take between 494 and 506 days. D. The activity will take between 476 and 524 days.

874

If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

940

You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar

1108

You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar

1163

You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is over allocated. Which of the following is true? A. You should use resource requirements updates to determine availability and smooth out resource over allocation. B. You should use crashing to resource level the critical path tasks. C. You should use resource leveling heuristics to smooth out resource assignments. D. You should use fast tracking to resource level the critical path tasks.

1 2571

What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

993

Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.

1446

Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools

910


Post New Project Management Questions

Un-Answered Questions { Project Management }

Project managers spend what percentage of their prime communicating? A. 90 B. 85 C. 75 D. 50

880


Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project? A. The strategic plan, because you'll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is similar in nature. C. The product description, which would describe all the details of the run/walk program. D. Historical information from the recent blood drive project.

1251


Which of the following compression techniques increases risk? A. Crashing B. Resource leveling C. Fast tracking D. Lead and lag

1254


During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.

934


You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210

903


The theory that 85 percent of the cost of quality is a management problem is attributed to: A. Doming B. Kaizen C. Juran D. Crosby

1415


You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports

1022


You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. You've been given a budget of $12 million to complete this project. Resources are easily attained. Which of the triple constraints is the primary constraint for this project? A. Time, because the date cannot be moved B. Money, because the budget is set at $12 million C. Resources, because they're not fixed D. Quality, because the buildings have to be functional and safe

1171


You are refining the product description for your company's new line of ski boots. Which of the following is true? A. You are in the Initiation process of your project and know that the product description will contain more detail in this stage and that a decreasing amount of detail will be added to it as the project progresses. B. You are in the Planning process of your project and know that the product description will contain less detail in this stage and greater detail as the project progresses. C. You are in the Initiation process of your project and know that the product description should contain the most detail possible at this stage, as this is critical information for the Planning process D. You are in the Initiation process of your project and know that the product description will contain less detail in this stage and greater detail as the project progresses.

1039


During your project meeting, a problem was discussed and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received and e-mail from one of the meeting members saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is an example of which of the following conflict resolution techniques? A. Confrontation B. Forcing C. Smoothing D. Storming

978


You are the project manager for Changing Tides video games. You have produced a project network diagram and have updated the activity list. Which process have you just finished? A. The Activity Sequencing process, which identifies all the specific activities of the project B. The Activity Sequencing process, which identifies all the activity dependencies C. The Activity Duration Estimating process, which diagrams project network time estimates D. The Activity Duration Estimating process, which identifies all the dependent activities of the project

860


The amount of authority a project manager possesses can be related to: A. The project manager’s communication skills B. The organizational structure C. The amount of authority the manager of the project manager possesses D. The project manager's influencing skills

2288


You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true? A. You are in the Project Plan Execution process. B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project. C. You are in the Information Distribution process. D. Your project team could benefit from some team-building exercises.

843


The VP of customer service has expressed concern over a project you're involved in. His specific concern is that if the project is implemented as planned, he’ll have to purchase additional equipment to staff his customer service center. The cost is substantial and was not taken into consideration in the project budget. The project sponsor insists that the project must go forward as originally planned or the customer will suffer. Which of the following is true? A. The VP of customer service is correct. Since the cost was not taken into account at the beginning of the project, the project should not go forward as planned. Project initiation should he revisited to examine the project plan and determine how changes can be made to accommodate customer service. B. The conflict should be resolved in favor of the customer. C. The conflict should be resolved in favor of the project sponsor. D. The conflict should be resolved in favor of the VP of customer service.

972


Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects

988