All of the following are true regarding Pareto diagrams and Pareto theory except: A. Pareto diagrams are histograms. B. Pareto diagrams rank order factors. C. A small number of causes create the majority of problems. D. Pareto diagrams use two variables.
1069You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram
899Your project progressed as planned up until yesterday. Suddenly, an unexpected risk event occurred. You quickly devised a response to deal with this negative risk event using which of the following tools and techniques of Risk Monitoring and Control? A. Risk management plan updates B. Workarounds C. Corrective action D. Additional risk identification
1257You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Slowly but surely your programmers are taken off this project and reassigned to the executive director's hot new project. Which of the following type of project ending is this? A. Starvation B. Extinction C. Addition D. Integration
1159You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations
1222You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true? A. This project ended due to starvation because the funding was cut off B. This project ended due to integration because the resources were distributed elsewhere C. This project ended due to starvation because the resources were distributed elsewhere D. This project ended due to integration because the funding was cut off
1187All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction
939You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away. Which of the following is true? A. This project ended due to extinction because it was completed and accepted. B. This project ended due to integration because it was completed and accepted and the project manager moved on to a new project. C. This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films. D. This project ended due to integration because it was completed and accepted.
1185Which of the following processes are performed in the Closing process group and in what order? A. Administrative Closure then Contract Closeout B. Scope Verification then Administrative Closure C. Contract Closeout then Scope Verification D. Contract Closeout then Administrative Closure
1215You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification
1050Which of the following are the outputs of the Contract Closeout process? A. Project archives, formal acceptance and closure, contract file B. Contract file, formal acceptance and closure C. Project archives, contract file D. Contract file, formal acceptance and closure, lessons learned
901You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements
998You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and have reviewed the contracting process to identify lessons learned. What is the name of the tool and technique of Contract Closeout you used to perform this function? A. Procurement audits B. Performance reviews C. Performance audits D. Procurement reviews
1090All of the following are inputs to the Administrative Closure process except: A. Performance measurement documentation B. Product documentation C. Other project records D. Contract documents
910You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are gathering the documentation of the product of the project. This might include all of the following except: A. Technical specifications B. Electronic files C. Programming plans D. Performance measurements
963Post New Project Management Questions
During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.
What are the qualities of a good project manager?
What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action
You are the project manager for an outdoor concert event scheduled for 1 year from today. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You've decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll option for which contract type? A. Fixed price plus incentive B. Cost plus fixed fee C. Fixed price D. Cost plus incentive
What are the inputs to the Initiation process? A. Product description, strategic plan, project selection criteria, and historical information B. Product description, strategic plan, project overview document, and historical information C. Strategic plan, project overview document, feasibility study, and historical information D. Product description, strategic plan, constraints, and assumptions
You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.
Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT
You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.
You are a project manager for Cashiers systems. Your company produces cashiering systems and software for the retail industry. Your customer has requested a change to the product. You will handle this change using the scope change control system. All of the following are true except: A. Changes to product scope should be reflected in project scope. B. Project scope changes may result in adjustments to the performance measurement baselines. C. Changes to project scope should be reflected in the product scope. D. Scope changes may result in performance improvements.
You are the project manager for Lucky Stars Candies. You've identified the deliverables and requirements and documented them where? A. In the scope statement, which will be used as in input to the Scope Definition process B. In the scope definition document, which is used as an input to the Scope Planning process C. In the WBS, which is an output of the Scope Planning process D. In the WBS, which is a tool and technique of the Scope Definition process
You are a project manager for Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000 with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months. Which project should you recommend? A. Project Fish'n for Chips because its payback period is two months shorter than Project Picnic’s B. Project Fish'n for Chips because the costs on Project Picnic are unknown C. Project Picnic because Project Fish'n for Chips' payback period is four months longer than Project Picnic’s D. Project Picnic because Project Fish'n for Chips' payback period is two months longer than Project Picnic's
You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been canceled due to budget cuts. Which of the following is true? A. This project ended due to starvation because the funding was cut off B. This project ended due to integration because the resources were distributed elsewhere C. This project ended due to starvation because the resources were distributed elsewhere D. This project ended due to integration because the funding was cut off
Which of the following project-scheduling techniques allows for conditional and probabilistic treatment? A. GERT B. CPM C. PERT D. CPM and PERT
The project sponsor has approached you with a dilemma. The CEO announced at the annual stockholders meeting that the project you're managing will be completed by the end of this year. The problem is that this is six months prior to the scheduled completion date. It's too late to go back and correct her mistake, and stockholders are expecting implementation by the announced date. You must speed up the delivery date of this project. Your primary constraint before this occurred was the budget. What actions can you take to help speed up the project? A. Hire more resources to get the work completed faster. B. Ask for more money so that you can contract out one of the phases you had planned to do with in-house resources. C. Utilize negotiation and influencing skills to convince the project sponsor to speak with the CEO and make a correction to her announcement. D. Examine the project plan to see if there are any phases that can be fast tracked, and then revise the project plan to reflect the compression of the schedule.
Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects