You are the project manager for a custom home-building construction company. You are working on the model home project for the upcoming Show Homes Tour. The model home includes Internet connections in every room and talking appliances. You are working on the cost budget for this project. Which of the following is true? A. This process assigns cost estimates to project activities including risks and contingency plans. B. The cost baseline will be used to measure variances and future project performance. C. This process assigns cost estimates for expected future period operating costs. D. The cost baseline is the expected cost for the project.
1243Which of the following is displayed as an S-curve? A. Gantt B. Cost baseline C. Critical path D. PERT
1169All of the following are true regarding the project plan except: A. Some of its inputs are outputs from other Planning processes. B. It's used to guide the project executing and controlling processes and is the baseline used to measure project performance. C. It consists of one document that should be formally approved and signed by stakeholders. D. It contains things like the WBS, project schedule, and resource assignments.
1193You are a project manager for an international marketing firm. You are ready to assign resources to your new project using a work authorization system. All of the following are true except: A. Work authorization systems clarify and initiate the work for each work package. B. Work authorization systems are written procedures defined by the organization. C. Work authorization systems are tools and techniques of the Project Plan Execution process. D. Work authorization systems are an output of the Project Plan Execution process.
1049Your project is progressing as planned. The project team has comp up with a demo that the sales team will use when making presentations to perspective clients. You will do which of the following at your next stakeholder process. A. Report on the progress of the demo and note that it's a completed task B. Preview the demo for stakeholders and obtain their approval and sign-off C. Review the technical documentation of the demo and obtain approval and sign-off D. Report that the demo has been noted as a completed task in the information retrieval system
1095All of the following arc tools and techniques of the Project Plan execution process except: A. Project management information system B. Work authorization system C. Organizational policies D. General management skills
950You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. You are in charge of the network operations part of this project. An important deadline is approaching that depends on the successful completion of the testing phase. You've detected some problems with your hardware in the testing phase and discover that the hardware is not compatible with other network equipment. You take corrective action and exchange the hardware for more compatible equipment. Which of the following is true? A. This is not a corrective action involves human resources, not project resources. B. Corrective action is taken here to make sure the future project outcomes are aligned with the project plan. C. Corrective action is not necessary in this case as the future project outcomes aren't affected. D. Corrective action serves as the change request to authorize exchanging the equipment.
917You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true? A. You are in the Project Plan Execution process. B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project. C. You are in the Information Distribution process. D. Your project team could benefit from some team-building exercises.
887Which of the following processes serve as inputs to each other? A. Executing and Controlling B. Planning and Executing C. Planning and Controlling D. Executing and Initiation
1099You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.
923You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite sometime and are in the performing stage of Team Development. A new member has been introduced to the team. Which of the following is true? A. The Team Development process will start all over again with the storming stage. B. The team will continue in the performing stage. C. The Team Development process will start all over again with the forming stage. D. The team will start all over again at the storming stage but quickly progress to the performing stage. ?
1021You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite some time and are in the performing stage of Team Development. This stage of Team Development is similar to which of the following? A. Smoothing B. Achievement theory C. Hygiene theory D. Self-actualization
938Receivers in the communication model filter their information through all of the following except: A. Culture B. Knowledge of subject C. Conflict D. Language
953You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following? A. Achievement theory B. Expectancy theory C. Maslow's theory D. Contingency theory
1206What are the outputs of the Team Development process? A. Performance improvements, input to performance appraisals B. Input to performance appraisals, reward and recognition systems C. Performance improvements, input to performance appraisals, performance reports D. Work results, input to performance appraisals, performance reports
1013Post New Project Management Questions
Which performance measurement tells us what the projected total cost of the project will be at completion? A. ETC B. CPI C. SPI D. EAC
You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following to identify the variables that will have the greatest effect on project outcomes? A. Design of experiments B. Bench marking C. Benefit/cost analysis D. Flow charting
Lessons learned are used for all of the following except: A. To provide historical information that you can review during your next project B. To document employee performance C. To identify successes and failures on the project D. To record the causes of performance variances
You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following flowcharts to diagram the problems' causes and effects? A. Decision tree diagram B. Fishbone diagram C. Benchmark diagram D. Simulation tree diagram
All of the following are benefits of meeting quality requirements except: A. An increase in stakeholder satisfaction B. Less rework C. Low turnover D. Higher productivity
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification
You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and how the information should be stored and filed is which of the following? A. Scope management plan B. Communications management plan C. Information distribution plan D. Project charter
You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite some time and are in the performing stage of Team Development. This stage of Team Development is similar to which of the following? A. Smoothing B. Achievement theory C. Hygiene theory D. Self-actualization
What are the qualities of a good project manager?
What is tracing process? How this can be enabled?
Which of the following is true regarding the staffing management plan needed for project activities? It is an output of the Resource Planning process. A. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Resource Planning process. B. It details how and when staff resources will be brought on and take off the project. It is an output of the Organizational Planning process. C. It details how and when staff resources wilt be brought on and take off the project. It is an output of the Resource Planning process. D. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Organizational Planning process.
You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. This project requires accurate information exchange at all times during the life of the project. How many lines of communication exist among the project team members? A.36 B.41 C.18 D.34
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true? A. This project came about due to customer request, and the primary constraint is time B. This project came about due to market demand, and the primary constraint is time. C. This project came about due to market demand, and the primary constraint is quality. D. This project came about due to customer request, and the primary constraint is quality.
What are the Initiation process outputs? A. Project charter, historical information, and project manager identification and assignment B. Project charter, project manager identification and assignment, constraints, and assumptions C. Project charter, historical information, constraints, and assumptions D. Project charter, constraints, and assumptions