You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is over allocated. Which of the following is true?
A. You should use resource requirements updates to determine availability and smooth out resource over allocation.
B. You should use crashing to resource level the critical path tasks.
C. You should use resource leveling heuristics to smooth out resource assignments.
D. You should use fast tracking to resource level the critical path tasks.
explain the contents of menubar
You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. You've been given a budget of $12 million to complete this project. Resources are easily attained. Which of the triple constraints is the primary constraint for this project? A. Time, because the date cannot be moved B. Money, because the budget is set at $12 million C. Resources, because they're not fixed D. Quality, because the buildings have to be functional and safe
You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple tight strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. One of the business unit managers submitted a change through the change control system, which utilizes a CCB. Which of the following is true regarding the CCB? A. Describes how change requests are managed B. Requires all change requests in writing C. Approves or denies change requests D. Requires updates to the appropriate management plan
You are a project manager for the information technology division of a local satellite TV broadcasting company. This spring, the chief information officer for your company gave you the project to convert and upgrade all the PCs in the department to the latest release of a specific desktop application. Prior to this conversion, all manner of desktop software existed on machines throughout the company and had caused increasing problems with sharing files and information across the company. A lot of unproductive hours were spent typing information into several formats. This project came about as a result of which of the following? A. Technological advance B. Business need C. Customer request D. Legal requirement
You are the project manager for a web development project. You hold regular project status meetings and publish status reports on a timely basis. You know that communication is one of your most important functions. As such, all of the following are true except: A. Senders are responsible for sending clear, concise, complete messages. B. Receivers are responsible for understanding the message. C. Communication can be vertical or horizontal or both. D. Effective communication techniques include making eye contact, nodding, and asking clarifying questions.
You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. You are in charge of the network operations part of this project. An important deadline is approaching that depends on the successful completion of the testing phase. You've detected some problems with your hardware in the testing phase and discover that the hardware is not compatible with other network equipment. You take corrective action and exchange the hardware for more compatible equipment. Which of the following is true? A. This is not a corrective action involves human resources, not project resources. B. Corrective action is taken here to make sure the future project outcomes are aligned with the project plan. C. Corrective action is not necessary in this case as the future project outcomes aren't affected. D. Corrective action serves as the change request to authorize exchanging the equipment.
Your project sponsor has requested a cost estimate for the project. She would like the cost estimate to be as accurate as possible as this might be her one and only chance to secure the budget for this project due to recent cuts in special projects. You decide: A. To use analogous estimating techniques B. To use bottom-up estimating techniques C. To use top-down estimating techniques D. To use expert judgment techniques
what is a project management?
16 Answers Areva, GB Engineering, Proteans,
What is the triple constraint triangle in project management?
All of the following are inputs to the Administrative Closure process except: A. Performance measurement documentation B. Product documentation C. Other project records D. Contract documents
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification
Which of the following are the outputs of the Contract Closeout process? A. Project archives, formal acceptance and closure, contract file B. Contract file, formal acceptance and closure C. Project archives, contract file D. Contract file, formal acceptance and closure, lessons learned