1. if only 1 slab of a floor get sagged, how could be it
repaired?
2. if any footing gives the cube result, after 28 days less
than 16 n/mm2 in spite of 20 n/mm2 what are the remedies ?
Answers were Sorted based on User's Feedback
Answer / venu gopal
2 reasons for saging.1) bad staging/supports. 2) bad
design. any hw if it sagged it does noteffect the next slab
casting we can cast the next one. as far as repairing of
1st slab is consern we should have a graphical
representation of sag and find out the lowest level and
highest level plot them and with the help of this date we
can fix the floor level ilttle elevated than planned and
the sagged area should be concreted (screed concret) with
good mix as per site condition.
2.if it is a big footing we cannot remove and redo. so
remove the top 200mm concret by chiping and use proper
bonding agents and introduce few more rebars through the
coloun and anchor them to the old footing and change the
shape of the footing to a triangular shape with rebars and
re concrete the top surface and additional care to be taken
at the time of casting plinth beam it is better to redesign
the plinth beam to take more load which the coloum will
carry. Note. check the mix design and use skilled manpower
while casting cubes at site. also place them in water
immediately after removing from moulds (delay in this
activity will also cause cube failure)
Is This Answer Correct ? | 6 Yes | 0 No |
i am completely aggre with venu gopal answer. if possible
the send me your personal e-mail id i want send to you
quary of civil engineering aspect which is arise in my mind.
my e-mail id (rd_shah13156@yahoo.co.in)
Is This Answer Correct ? | 0 Yes | 1 No |
look if slab get sagged it better to be dismentaling and
construct new slab. by constructing new slab other floors
will not affect, because load carried by column.
your second question if cube result are below their
strength, as per is code it will better to be dismentaling.
Is This Answer Correct ? | 2 Yes | 7 No |
m30 mix proportion as per IS code
How many bricks required for 1 cu.m
What will be the maximum length of RCC Lintels?
What is the Laplenth for Reinforcement for Verticl and horizontal Structures as per IS code?
what are the minimum compressive strength required for the concrete cube for different grades & different days .Please give me an answer.
what is the basic fundamental of contouring?
6. What would your co-workers say about you?
how to calculate steel for beam of simple home and for heavy buliding ? explain me briefly
what is the IS code no. for concrete wastage?
how much M-25 steel reinforcement per cubic meter in commercial building as per IS code
What is lever arm distance
How do you maintain water pressure?