we want install 11KV generator to supply power 12km far
from the power house.Load to be fed is 1MW.which conductor
should we use and wat will be transmission line losses?



we want install 11KV generator to supply power 12km far from the power house.Load to be fed is 1MW..

Answer / k.prakashchandra

The current is 52.5 A at unity pf, add 20 % .It is about 60
A. You can use Rabbit conductor

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Electrical Engineering Interview Questions

I NEED RRB SYLABUS FOR JE ELECTRICAL ,PLEASE SEND TO MY E- MAIL ID joo28_eee@yahoo.co.in

0 Answers  


1. what is the power factor of a purely inductive load? (i) Zero (ii) Lagging (iii)Leading (iv) Unity 2. which type of transformer connection is preferred in case of power supply transformer? (i) Star/Star (ii) Delta/Delta (iii) Star/Delta (iv) Zig Zag/Star

2 Answers  


What is the meaning of GRID?

21 Answers  


hi frnds...pls send me aptransco previous papers .....pls..pls,,,(madhar.rocking@gmail.com)and suggest me some websites

0 Answers  


what is the method of earthing of a transformer using electrodes?

0 Answers  






The SFC of an engine is 0.25 kg/kW hr. when the fuel used has a calorific value of 36000 kJ/kg. the thermal efficiency of the engine is

0 Answers   Caterpillar,


what r Grid stations?what r there role.Explain in detail

1 Answers  


Capacitor is load free component but why ampere meter shows current when capacitor bank breaker close?

0 Answers  


Do I need a special Transformer to put 240 VAC 3 phase into it and and get 480 VAC 3 phase out of it to run a machine? Or, do I just use an ordinary step down transformer and step up the voltage? Thanks

2 Answers  


is the secondary voltage of current transformer greater than primary voltage,,,,,,,,] give the example with ct burden,current ratio,and primary and secondary side voltage?

2 Answers  


WHY WE ARE EXPRESSING KW-HR AS UNIT OF ELECTRICITY.........?WE CAN EXPRESS IN ANOTHER UNIT.....?

4 Answers   Summit Power,


Lt trivector meter with ring type CT.Spec of meter are 3x240 v, -/5A. Ring ct spec. are 60/5A, line voltage- IL .66/3.0KV..what is the multiplying factor

1 Answers  


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)