Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


cable selection formulas for electrical load.



cable selection formulas for electrical load...

Answer / engineered

Factors for selection of cable
1.Rated current
2.voltage drop across cable
3.derating factor based on temprature,no. of cables laid
through same path influencing each other
4. Type of laying method:- like air, ground, duct, tray,
raceway
5. type of conductor required.
6. type of insulation, like PVC, XLPE, FRLS based on site
condition

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More Electrical Engineering Interview Questions

Explain what is rated speed?

0 Answers  


Between AC generator(alternator) and DC generator which can be designed for high voltage and why?

1 Answers  


WHAT DO U MEAN BY THERMAL OVER LOAD RELAY& WHERE THEY ARE BUSED

4 Answers   L&T,


why America use 60HZ 110V?

4 Answers   Kalindee Rail,


why the motor is rated as kw& transformer as kva

7 Answers   Areva,


what is the cause of voltage dipp or swell in the transmission lines?

0 Answers  


how fluoresent lamp works??

2 Answers  


WHAT IS SITTING AMPS IN OVER-LOAD RELAY FOR 1PH OR 3PH MOTORS?IF ITS NAME PLATE GIVEN MAX AMPS 10AMPS?

0 Answers  


EXPLAIN THE FOLLWING: (1) BANDWIDTH (2) SELECTIVITY (3) RESONANT FREQUENCY (4) CURRENT MAGNIFICATION

1 Answers  


We have three 33kv substations. All of them energised by same source.When i am checking the phase sequence between one substation to other substation (like R Phase to R Phase) by multimeter i am getting some voltage.Near to LT panels UPS panels are there. Can u explain whether any possible to happen like that. In Phase SEquencemeter is showing correctly in both substations. How is it happen. Explain me.Explain me communication signal will produce Phase difference on this case.

3 Answers  


In a overhead system why the voltage between line &ground is taken for basic comparison ?and in case of underground cables the comparison take only by the voltage between cables?

1 Answers   L&T,


what is the difference between ups & inverter

4 Answers   Cushman Wakefield, Dana Group,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)