Answer / m.waqas(electrical)
both of the techniques are the same .
IN polarization index method the molecules of water are polarized and it takes almost ten mints to polarize the water molecule by using megger. This test is performed in field or you can say on used transformer or on that transformer which remain idle (not in use for long time with oil present in it) where there is a chance of moister presence due to condensation.
The dielectric absorption technique is used for type test(test perform after making transformer) here transformer is new and moister is just remove. As we all know absorption method is quicker than that of polarization(ratio of resistance measured 15 sec to 1 minit ).
BUT polarization technique is always preferred for good results or reliable results.
| Is This Answer Correct ? | 1 Yes | 0 No |
tell 2 reasons for why only copper is used in domestic wires& only alluminium in transmission lines ?
why we use star connection in HT motor? and delta connection in LT motor
Explain the propagation of harmonics in the network and influence of phase angle of harmonics.
Formula to calculate fault current flowing in the neutral line?
What is main cause of cable's terminal point burned in Lug on high temperature although lug and cable selection is ok as per stantard and also tightness is ok as per situation. so please take in deep and tell correct answer thanku.
TO CALCULATE THE RESISTANCE OF GRR OF HT MOTOR 400KW WHEREAS STATOR VOLTAGE 6.6KV AND ROTOR VOLTAGE 705V AND ROTOR CURRENT IS 346A.
what is power factor
what is the difference between rccb and elcb?
can we use inductor for passing or blocking of AC or DC?
1)Explain why the cradle guard is used on railway crossing in overhead line construction?
Tesla is the unit of which parameter?
We are installing a 1.6 MVA transformer at our crusher plant and the feeder of HPSEBL is 2 km away at substaion . and a VCB is installed in the substaion which is 2 km away from transformer so we need another VCB near the transformer.
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)