How do you monitor risks to the project and mitigate them?
Answer / hardik desai
We have to first analyzed the risk of a project based on
statistical probability and categorized as the following
ratings.
Probability:
High The risk is more likely to occur. À50%
Medium The risk is about as likely to occur as not to
occur. ¼ 50%
Low The risk is more likely not to occur. ¿50%
Severity:
High This risk, unmitigated, would result in a complete
failure for the project.
Medium This risk would have a major impact on the project’s
schedule, cost, or performance.
Low This risk would have a minor impact on the project.
1) Analyze Risks
Based on the ratings given to each risk, they will be
analyzed to determine what action the project
will take. That action could include immediate programatic
changes to ensure that the risk does not
occur, development of mitigation plans that could be
implemented in the event of the occurence of the
risk, or some other action as appropriate.
2) Monitor Risks
Every effort will be made to ensure that the risks do not
occur, and if they do occur, that we notice the
occurence of the risk as soon as possible. Early notice can
help us limit any possible negative effects of
the risk on the project. If progression of the project
changes the assessment of the probability or severity
of a risk, the risk will be analyzed and the RMP will be
updated.
3) Mitigate Risk
In the event that a risk does occur, the issue will be
analyzed in light of the mitigation plans and
action will be taken as appropriate.
Is This Answer Correct ? | 43 Yes | 15 No |
What is security policy? To protect an organization’s information what security policy need to follow according to you.
Which managerial function gives attention to influencing and motivating employees to improve performance and achieve corporate objectives?
What are the Roles and Responsibilities of BDM in IT Industry ? And Tell me some thing about about IT industries
When you are given to develop a computer based information system for banking, how do you write the SDLC diagram?. Explain the five phases with respect to banking.
What id the meaning of MIS ? MIS nasure, charactersitcs, purpose ? how can the leanr about them ?
what is variable?
Why general ledger accounts require "post automatically" setting in SAP??
state the role of cost accounting in large scale industry
DataStage 7.5 & DataStage 8.5 :Which Oracle Database version is supported as target datasource?
Write a C Program to create a structured data file named Student.dat to store the roll no, name and course. Provide following functions: 1. Accept the values from the user using structure variables. Store the contents in a file. 2. Display the file. 3. The user should be able to add new records to the existing file. And display the new file.
4 Answers ABC, Chowgule, CMS, CSC, IBM, Practical Viva Questions, Student, Symbiosis, University Exams,
why do you join mba in IT sector?
Write a C Program to declare an array for 2 0 floats. Accept the values from the user sort the two arrays in descending order. Merge the two arrays into a new array and display the new array.
1 Answers EWR, MAH, SCDL Symbiosis Center for Distance Learning, Symbiosis,