Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?

Answers were Sorted based on User's Feedback



Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / bj

Check back with your specifications regarding the server
requirements. If the requirement was never specified, you
have assumed that the requirement is a 32 bit system.

In this situation, list the possible reasons why it failed.
Run a system test on a 32 bit machine and doubly ensure that
the reason for failure in only the server specification

Schedule a meeting with the customer and let them know that
the UAT failed and the most probable reason being he server
specification. Provide them the list of other possible
reasons (if you found any) and also inform them about your
plans on how to plan to tackle the issue and your
guesstimate of the time for the same.

Based on the criticallity of the system, one of the
solutions could be to deploy the software system on a 32 bit
server while you figure out a way to fix the issue. This
option could be given to the customer.

It is quite possible that the customer would take this
option and this would save time for the customer and help
your team to quickly find a fix.

Otherwise go with whatever the customer thinks you should do.

Is This Answer Correct ?    19 Yes 0 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / veerendra kumar

First of all we need to react to this situation more in a
technical way, many of the 64 bit OS are supporting 32 bit
applications. First verify if the OS can support 32 bit app
on the UAT or PROD server, 99% OS would have drivers to run
32 bit apps.

In the worst situation you may go with 32 bit system till
your app gets covert on to 64 bit.

Is This Answer Correct ?    5 Yes 4 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / yogesh

There is not a signle answer for this situation , I faced
this problem , and faced critisim also. I changed the
process steps as part of the reaction.

Assumptions are the most critical factors when PM work out
the planning stage.

As PM it should have been noticed in requirement and test
case reviews about the various platform compatibility
checks.

But this requirement missed totally, in this case,estimate
and negoiate with the customer and ask for the new time
lines for phase by phase migration to 64 bit platform.
Mostly the impact will be on projct cost and who will be
accounted for.

Is This Answer Correct ?    1 Yes 0 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / sreedhara

First Analyze the problem throughly, it is technical problem or requirements mismatch problem or your team developed in 32 bit environment. First test a sample code on the 64 bit environment at development box and ensure it runs with out problem. Then estimate who much extra efforts are required to complete conversion, can we do in module wise or drops (agile method), finalize all these things at your end then approach the customer about the issue, with all the solutions and efforts. Before that ensue that all these things are not captured in the issue log (issues, risks & assumptions).

Is This Answer Correct ?    0 Yes 3 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / shri

having 1 round of testing on 64 bit environment

Is This Answer Correct ?    0 Yes 4 No

Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find..

Answer / ck

First list out the possible reasons why it is failed and
also list out possible solutions...Then inform the customer
with effort required if possible with revised dates

Is This Answer Correct ?    0 Yes 7 No

Post New Answer

More Project Management Interview Questions

Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques

0 Answers  


What is the difference between project, program, and portfolio?

0 Answers  


Your project involves the research and development of a new food additive. You’re ready to release the product to your customer when you discover that a minor reaction might occur in people with certain conditions. The reactions to date have been very minor, and no known long-lasting side effects have been noted. As project manager you should: A. Do nothing because the reactions are so minor that very few people will be affected. B. Inform the customer that you've discovered this condition and tell them you'll research it further to determine the impacts. C. Inform your customer that there is no problem with the additive release the product to them. D. Tell the customer you'll correct the reaction problems in the next batch but you'll release the first batch of product to them now to begin using.

0 Answers  


Which of the following are the outputs of the Contract Closeout process? A. Project archives, formal acceptance and closure, contract file B. Contract file, formal acceptance and closure C. Project archives, contract file D. Contract file, formal acceptance and closure, lessons learned

0 Answers  


All of the following are benefits of meeting quality requirements except: A. An increase in stakeholder satisfaction B. Less rework C. Low turnover D. Higher productivity

0 Answers  






You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time

0 Answers  


You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. As project manager, you have taken all the appropriate actions regarding confidentiality of data. One of the key stakeholders is a huge movie huff, and she has the power to promote you into a better position at the conclusion of this project. She's reviewing some report data that just happens to include confidential information regarding one of her favorite movie superstars. What is the most appropriate response? A. Report her to the management team. B. Request that she immediately return the information, citing conflict of interest and violation of confidential company data. C. Do nothing as she has the proper level of access rights to the data and this information showed up unintentionally. D. Request that she immediately return the information until you can confirm that she has the proper level of access rights to the data.

0 Answers  


You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.

0 Answers  


Describe capability maturity model (cmm).

0 Answers  


Many times software delivery is late, why? Give reason.

0 Answers  


Your hardware vendor left you voicemail saying that a potential snowstorm in the Midwest might prevent your equipment from arriving on time. She wanted to give you a heads-up and asked that you return the call. Which of the following is true? A. This is a secondary risk, which is an output of Risk Response Planning. B. This is a contingency plan, which is an output of Risk Response Planning. C. This is a risk, which is an output of Risk Identification. D. This is a trigger, which is an output of Risk Identification.

0 Answers  


You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. One of your users verbally requests changes to one of the screen displays. You explain to her that the change needs to go through the change control system. You explain that a change control system does all of the following, except: A. Document procedures for change requests B. Track the status of change requests C. Describe the management impacts of change D. Determine if changes are approved or denied

0 Answers  


Categories