Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?
Answers were Sorted based on User's Feedback
Answer / bj
Check back with your specifications regarding the server
requirements. If the requirement was never specified, you
have assumed that the requirement is a 32 bit system.
In this situation, list the possible reasons why it failed.
Run a system test on a 32 bit machine and doubly ensure that
the reason for failure in only the server specification
Schedule a meeting with the customer and let them know that
the UAT failed and the most probable reason being he server
specification. Provide them the list of other possible
reasons (if you found any) and also inform them about your
plans on how to plan to tackle the issue and your
guesstimate of the time for the same.
Based on the criticallity of the system, one of the
solutions could be to deploy the software system on a 32 bit
server while you figure out a way to fix the issue. This
option could be given to the customer.
It is quite possible that the customer would take this
option and this would save time for the customer and help
your team to quickly find a fix.
Otherwise go with whatever the customer thinks you should do.
| Is This Answer Correct ? | 19 Yes | 0 No |
Answer / veerendra kumar
First of all we need to react to this situation more in a
technical way, many of the 64 bit OS are supporting 32 bit
applications. First verify if the OS can support 32 bit app
on the UAT or PROD server, 99% OS would have drivers to run
32 bit apps.
In the worst situation you may go with 32 bit system till
your app gets covert on to 64 bit.
| Is This Answer Correct ? | 5 Yes | 4 No |
Answer / yogesh
There is not a signle answer for this situation , I faced
this problem , and faced critisim also. I changed the
process steps as part of the reaction.
Assumptions are the most critical factors when PM work out
the planning stage.
As PM it should have been noticed in requirement and test
case reviews about the various platform compatibility
checks.
But this requirement missed totally, in this case,estimate
and negoiate with the customer and ask for the new time
lines for phase by phase migration to 64 bit platform.
Mostly the impact will be on projct cost and who will be
accounted for.
| Is This Answer Correct ? | 1 Yes | 0 No |
Answer / sreedhara
First Analyze the problem throughly, it is technical problem or requirements mismatch problem or your team developed in 32 bit environment. First test a sample code on the 64 bit environment at development box and ensure it runs with out problem. Then estimate who much extra efforts are required to complete conversion, can we do in module wise or drops (agile method), finalize all these things at your end then approach the customer about the issue, with all the solutions and efforts. Before that ensue that all these things are not captured in the issue log (issues, risks & assumptions).
| Is This Answer Correct ? | 0 Yes | 3 No |
Answer / ck
First list out the possible reasons why it is failed and
also list out possible solutions...Then inform the customer
with effort required if possible with revised dates
| Is This Answer Correct ? | 0 Yes | 7 No |
What are decision models? A. Project selection criteria B. Project selection methods C. Project selection committees D. Project resource and budget selection criteria
Which of the following processes negotiates the sequence of award by rank ordering the proposals? A. Source Selection B. Solicitation C. Contract Administration D. Procurement
Which performance measurement is the cost of work budgeted for an activity within a certain time frame? A. AV B. PV C. EV D. EAC
What are the tools for process improvement?
You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are gathering the documentation of the product of the project. This might include all of the following except: A. Technical specifications B. Electronic files C. Programming plans D. Performance measurements
You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.
How do you motivate team members?
You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following flowcharts to diagram the problems' causes and effects? A. Decision tree diagram B. Fishbone diagram C. Benchmark diagram D. Simulation tree diagram
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and several time estimates and are ready to diagram the activity dependencies. You should use which of the following? A. PDM techniques B. PDM or ADM techniques C. AON techniques D. ADM techniques
You are a project manager with several years of experience in project management. You’ve just accepted your first project in a foreign country. You've been in the country a week or two and are experiencing some disoriented feelings. This is known as: A. Collocation B. Diversity shock C. Global culturing D. Culture shock
You are a project manager for Zippy Tees. Your selection committee has just chosen a project you recommended for implementation. Your project is to manufacture a line of miniature stuffed bears that will be attached to your company's trendy T-shirts. The bears will be wearing the same T-shirt design as the shirt they're attached to. Your project sponsor thinks you've really impressed the big boss and wants you to skip to the manufacturing process right away. What is your response? A. To agree with the project sponsor because they are your boss, and they have a lot of authority and power in the company. B. To require that a preliminary budget be established and a resource list be put together to alert other managers of the requirements of this project. This should be published and signed by the other managers who are impacted by this project. C. To require a project charter be published and signed off on by all stakeholders before proceeding. D. To require a project charter be written to include the resource needed, budget, and project manager's authority. The project manager is the only one who needs to see this document as other documents will be distributed later that contain the same detail as the charter.
The product description, strategic plan, project selection criteria, and historical information are considered: A. Inputs to the project Planning process B. Inputs to the project Overview process C. Inputs to the project Initiation process D. Inputs to the project Execution process