Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?
Answer Posted / bj
Check back with your specifications regarding the server
requirements. If the requirement was never specified, you
have assumed that the requirement is a 32 bit system.
In this situation, list the possible reasons why it failed.
Run a system test on a 32 bit machine and doubly ensure that
the reason for failure in only the server specification
Schedule a meeting with the customer and let them know that
the UAT failed and the most probable reason being he server
specification. Provide them the list of other possible
reasons (if you found any) and also inform them about your
plans on how to plan to tackle the issue and your
guesstimate of the time for the same.
Based on the criticallity of the system, one of the
solutions could be to deploy the software system on a 32 bit
server while you figure out a way to fix the issue. This
option could be given to the customer.
It is quite possible that the customer would take this
option and this would save time for the customer and help
your team to quickly find a fix.
Otherwise go with whatever the customer thinks you should do.
Is This Answer Correct ? | 19 Yes | 0 No |
Post New Answer View All Answers
Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.
Each of the following is true regarding the risk management plan except: A. The risk management plan is an output of the Risk Management Planning process B. The risk management plan includes a description of the responses to risks and triggers. C. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets. D. The risk management plan is an input to all the remaining risk planning processes.
Explain the Principals of Management
You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
This process applies evaluation criteria to the bids and proposals received from potential vendors: A. Solicitation B. Contract Administration C. Source Selection D. Quality Assurance
You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You're heading up a project to promote a new line of souvenirs to be sold at the shows. You're ready to write the scope statement, and you know it should contain which of the following? A. Project justification, benefit/cost analysis, project deliverables, and product analysis B. Product analysis, project product, and project deliverables C. Project justification, project product, project deliverables, and project objectives D. Product analysis, project deliverables, benefit/cost analysis, and project objectives
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You've been told that it is culturally unacceptable to eat certain foods in this country. You know that one of these foods happens to be a secret ingredient in the pizza sauce. What is the most appropriate response? A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it. B. Inform the potential partners that you suspect there might be a forbidden ingredient in the sauce and you'll request an investigation to determine if any of them exist in the sauce. C. Inform the potential partners that a forbidden ingredient exists in the sauce and determine to work with them to come up with another ingredient to replace that one. D. Don't tell the potential partners about the ingredient because the sauce they'll be using in the stores is shipped to them already prepared in cans. They won't know the ingredient is in the sauce.
You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You have been invited to dinner with the prospective foreign business partners and their spouses upon your arrival. You know that all of the following are generally true except: A. You should spend time building relationships with your prospective foreign business partners before getting down to business. B. You should explain your company's rules, standards, and operating policies at your first meeting with the prospective foreign business partners. C. You should build an atmosphere of mutual trust and cooperation. D. You should respect the cultural differences you'll encounter when working with your prospective foreign business partners.
You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity
You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations
Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14
You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.
All of the following are true regarding configuration management except: A. Requires all acceptance decisions to be made through the CCB B. Serves as a change control system C. Describes the physical characteristics of the product of the project D. Controls changes to the characteristics of an item or system
As a project manager, you're responsible for maintaining and ensuring integrity for all of the following except: A. Personal integrity of others B. Project management process C. Personal integrity D. Product integrity
The Project Integration Management knowledge area is made up of which of the following processes? A. Initiation, Project Plan Development, and Integrated Change Control B. Project Plan Development, Project Plan Execution, and Integrated. C. Project Plan Development, Initiation, and Scope Planning D. Initiation, Scope Planning, and Integrated Change Control