Suppose you did all your work in a 32 bit system, the
production server is 64 bit system, you find that during
UAT, the system fails and is not working, how will u
communicate to your customer, what solution will you
provide to the client?
Answer Posted / ck
First list out the possible reasons why it is failed and
also list out possible solutions...Then inform the customer
with effort required if possible with revised dates
Is This Answer Correct ? | 0 Yes | 7 No |
Post New Answer View All Answers
The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package
Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects
Integrity in the project management field is accomplished through all of the following except: A. Training to learn how to manage relationships with others from different cultures B. Adhering to an ethical code C. Applying established project management processes D. Following the Project Management Professional Code of Professional Conduct
This tool and technique of Quality Control keeps errors from reaching the customer: A. Inspection B. Prevention C. Corrective action D. Performance measurement
Which performance measurement tells us how much more of the budget is required to finish the project? A. ETC B. EV C. AC D. EAC
You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150
You are project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a project charter should be published prior to proceeding to the Planning processes. All of the following are true regarding project charters except: A. Project charters always include cost and time estimates. B. Project charters always include the product description and business need for the product. C. Project charters recognize and acknowledge the existence of the project. D. Project charters commit organizational resources to the project.
You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors invites you to lunch. What is the most appropriate response? A. Thank them but let them know this could be a conflict of interest since you haven't made a decision about which vendor you're going to choose. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. You don't believe there is a conflict of interest or a personal integrity issue. D. Thank them and decline. You believe this could be a conflict of interest on the part of the vendor, and you don't want to encourage that behavior.
Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?
Which of the following contracts should you use for projects that have a degree of uncertainty and require a large investment early in the project life cycle? A. Fixed price B. Cost reimbursable C. Lump sum D. Unit price
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. This information might be useful on future projects in all of the following activities except: A. Cost estimating B. Allocating resources C. Product verification D. Activity estimating
All of the following are tools and techniques of the Quality Control process except: A. Monte Carlo Analysis B. Statistical sampling C. Pareto diagrams D. Trend analysis
You have been asked to submit a proposal for a project that has been put out for bid. Prior to submitting the proposal, your company must register so that their firm is on the qualified seller list. Which of the following is true? A. The qualified seller list provides information about the sellers and is a tool and technique of the Solicitation process. B. The qualified seller list provides information about the project and the company that wrote the RFP and is an input to the Solicitation process. C. The qualified seller list provides information about the project and the company that wrote the RFP and is a tool and technique of the Source Selection process. D. The qualified seller list provides information about the sellers and is an input to the Solicitation process.
You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. Resources are not readily available as they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project? A. Negotiation and influencing skills B. Communication and organizational skills C. Communication skills D. Problem-solving skills
Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues. Which of the following should you consider? A. Corrective action B. Collocation C. Training D. Conflict resolution