How to deal with underperforming team members?
No Answer is Posted For this Question
Be the First to Post Answer
The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates
Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true? A. This project came about due to customer request, and the primary constraint is time B. This project came about due to market demand, and the primary constraint is time. C. This project came about due to market demand, and the primary constraint is quality. D. This project came about due to customer request, and the primary constraint is quality.
Explain the difference between Project management and IT management.
What is eXtreme methodolgy ?
You work for a company that writes hilling software programs for the communication industry. You've just been assigned a new project. The customer is located in a distant country that limits the number of foreigners allowed into the country. You identify this risk in your risk management plan. The critical point during the project is installation and setup. You might do which of the following given these circumstances? A. Use a design of experiments technique to develop a contingency plan. B. Develop a cause-and-effect diagram that identifies the contract type you should use for a project like this. C. Use sensitivity analysis to assist you in developing the appropriate risk response for this situation. D. Develop a contingency plan for installation.
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.
Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.
What is "Readjustig goal and Milestone" in project managment and project planing
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
Which performance measurement tells us what the projected total cost of the project will be at completion? A. ETC B. CPI C. SPI D. EAC
How project comes to a software company? what is the role of sales department,marketing department,delivery manager,project manager in a software development? simply,what is project life cycle?