All of the following are true regarding parametric modeling except:
A. It's a form of top-down estimating.
B. It's a mathematical model.
C. It's a tool used to estimate project costs.
D. It's a tool used to estimate project time.
No Answer is Posted For this Question
Be the First to Post Answer
Which of the following compression techniques increases risk? A. Crashing B. Resource leveling C. Fast tracking D. Lead and lag
Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published the scope statement and the supporting detail. The supporting detail contains all of the following except: A. Constraints B. Other project information not noted in the scope statement C. Code of accounts D. Assumptions
What are the inputs to the Initiation process? A. Product description, strategic plan, project selection criteria, and historical information B. Product description, strategic plan, project overview document, and historical information C. Strategic plan, project overview document, feasibility study, and historical information D. Product description, strategic plan, constraints, and assumptions
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration
You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure does this represent? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization
Your project has experienced some changes to the agreed-upon WBS elements. The changes were approved through the proper change control process. The WBS changes may in turn require which of the following? A. Scope changes B. Cost changes C. Schedule revisions D. Risk response changes
You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite sometime and are in the performing stage of Team Development. A new member has been introduced to the team. Which of the following is true? A. The Team Development process will start all over again with the storming stage. B. The team will continue in the performing stage. C. The Team Development process will start all over again with the forming stage. D. The team will start all over again at the storming stage but quickly progress to the performing stage. ?
Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates
You are the project manager for an outdoor concert event scheduled for 1 year from today. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You've decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll option for which contract type? A. Fixed price plus incentive B. Cost plus fixed fee C. Fixed price D. Cost plus incentive
As project manager, you know that all of the following are true concerning analogous estimating techniques except: A. It's a qualitatively based estimating technique. B. It's a top-down estimating technique. C. It's a tool and technique of Activity Duration Estimating and Cost Estimating. D. It’s a form of expert judgment.
You are a project manager and are in the Closing process of the project. Your customer has been presented with a formal acceptance and sign-off document. They refuse to sign, claiming the product does not meet their expectations. You know that this situation could have been prevented by doing all of the following except : A. Documenting the requirements B. Documenting the customer's refusal to sign C. Performing quality inspections during the process D. Requesting sign-off at important milestones