What is the w5hh (wwwwwhh) principle given by barry boehm?
No Answer is Posted For this Question
Be the First to Post Answer
Your hardware vendor left you voicemail saying that a potential snowstorm in the Midwest might prevent your equipment from arriving on time. She wanted to give you a heads-up and asked that you return the call. Which of the following is true? A. This is a secondary risk, which is an output of Risk Response Planning. B. This is a contingency plan, which is an output of Risk Response Planning. C. This is a risk, which is an output of Risk Identification. D. This is a trigger, which is an output of Risk Identification.
Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.
Which of the following brings together a set of tools and techniques used to describe, organize, and monitor the work of project activities? A. Project managers B. Guide to the PMBOK C. Project management D. Stakeholders
Your company is going to introduce a new service called Phone Home. This service will allow you to speak the name of the person you want to call into your cellular phone. To call home, you would simply speak the word home into the phone, and it will dial that number for you. Your company is taking advantage of the progress that has been made recently with voice recognition software. Initial projections show that market demand is very high for this product. This project came about as a result of which of the following? A. Marketing demand B. Customer request C. Business need D. Technological advance
What are the outputs of the Team Development process? A. Performance improvements, input to performance appraisals B. Input to performance appraisals, reward and recognition systems C. Performance improvements, input to performance appraisals, performance reports D. Work results, input to performance appraisals, performance reports
What are the outputs of the Scope Planning process? A. Product analysis, scope statement, and scope management plan B. Scope statement, scope management plan, and WBS C. Scope statement, supporting detail, and WBS D. Scope statement, supporting detail, and scope management plan
You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75
Comparative methods, scoring methods, and economic and cash flow analysis are all part of which of the following? A. Benefit measurement methods, which are a tool and technique in Initiation B. Constrained optimization methods, which are a tool and technique C. Benefit measurement methods, which are an input to Initiation D. Decision models, which are an output of Initiation
Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find that during UAT, the system fails and is not working, how will u communicate to your customer, what solution will you provide to the client?
HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta
You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram
You are a project manager for a documentary film company. In light of a recent national tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic firefighters to air as soon as possible. She's looking to you to make this documentary the best that's ever been produced in the history of this company. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photographer in the company is currently working on another assignment. Which of the following is true? A. The primary constraint is time because the president wants the film done quickly. She told you to get it to air as soon as possible. B. Resources are the primary constraint. Even though the president has given you free rein on resource use, you assume she didn't mean those actively assigned to projects. C. The schedule is the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects. The photographer won’t be finished for another three weeks on his current assignment, so schedule adjustments will have to be made. D. The primary constraint is quality because the president wants this to be the best film ever produced by this company. She's given you free rein to use whatever resources needed to get the job done.