Project managers spend what percentage of their prime communicating?
A. 90
B. 85
C. 75
D. 50
No Answer is Posted For this Question
Be the First to Post Answer
You are constructing a probability/impact risk rating matrix for your project. Which of the following is true? A. The PI matrix multiplies the risk's probability by the cost of the impact to determine an expected value of the risk event. B. The PI matrix multiplies the risk's probability scales, which fall between 0.0 and 1.0, and the risk’s impact scales to determine a risk score. C. The PI matrix multiplies the risk's probability by the expected value of the risk event to determine the risk impact and assign a risk score based on a predetermined threshold. D. The PI matrix multiplies the risk's probability scales and the risk's impact scales, which fall between 0.0 and 1.0, to determine a risk
This measurement is the value of the work that's been completed to date: A. PV B. AC C. EV D. EAC
You are project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a project charter should be published prior to proceeding to the Planning processes. All of the following are true regarding project charters except: A. Project charters always include cost and time estimates. B. Project charters always include the product description and business need for the product. C. Project charters recognize and acknowledge the existence of the project. D. Project charters commit organizational resources to the project.
what kind of questions can be asked from SDLC for a project leader role?
The VP of marketing approaches you and requests that you change the visitor logon screen on the company’s website to include a username with at least six characters. This is considered: A. Project initiation B. Ongoing operations C. A project D. Project execution
Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.
HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta
You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management
You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following? A. Achievement theory B. Expectancy theory C. Maslow's theory D. Contingency theory
All of the following are true regarding the project plan except: A. Some of its inputs are outputs from other Planning processes. B. It's used to guide the project executing and controlling processes and is the baseline used to measure project performance. C. It consists of one document that should be formally approved and signed by stakeholders. D. It contains things like the WBS, project schedule, and resource assignments.
All of the following are true regarding the ADM method except: A. It's a tool and technique of Activity Sequencing. B. It uses one time estimate to determine durations. C. It's also called AOA. D. It's rarely used today.
You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75