You are a project manager for a growing dairy farm. They offer their organic dairy products regionally and are expanding their operations to the West Coast. They're in the process of purchasing and leasing dairy farms to get operations under way. The sub project manager in charge of network operations has reported some hardware problems to you. You’re also having some other coordinating and integrating other elements of the project. Which of the following is true?
A. You are in the Project Plan Execution process.
B. Your project team doesn't appear to have the right skills and knowledge needed to perform this project.
C. You are in the Information Distribution process.
D. Your project team could benefit from some team-building exercises.
No Answer is Posted For this Question
Be the First to Post Answer
What is the concept of project management?
You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.
You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope. Which of the following is true? A. Project scope changes do not require CCB approval. B. Performance measurement baselines are affected by scope changes. C. Project scope change uses inspection to determine if change has occurred. D. Project scope change uses workarounds to correct unexpected problems with scope change.
You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Arizona or Nevada. You have derived the following information: Project Arizona: Payback period is 18 months, and the NPV is 250. Project Nevada: Payback period is 24 months, and the NPV is 300. Which project would you recommend to the selection committee? A. Project Arizona because the payback period is shorter than Project Nevada B. Project Nevada because the NPV is a positive number C. Project Arizona because the NPV is a negative number D. Project Nevada because the NPV is a higher number than Project Arizona's NPV
Which of the following is true regarding the Resource Planning process? A. Resource Planning involves the human resource aspect of planning only, and its output is staffing requirements. B. Resource Planning involves the human resource aspect of planning only, and its output is staffing requirements. C. Resource Planning encompasses all the physical resources needed for the project, and its output is staffing requirements. D. Resource Planning encompasses all the physical resources needed for the project, and its output is resource requirements.
What are the characteristics of management?
0 Answers Mahatma Gandhi University,
Why do you want to switch over from IT to management?
You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following? A. Procurement planning B. Sensitivity analysis C. Transference of risk D. Make or buy analysis
Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.
Describe function-oriented metrics.
Project managers have the greatest amount of authority in which kind of organizational structure? A. Functional B. Projectized C. Weak matrix D. Balanced matrix
What are the different software reengineering activities?