You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except:
A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration.
B. You terminate the contract for poor performance and submit a change request through Contract Administration.
C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract.
D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.
No Answer is Posted For this Question
Be the First to Post Answer
The purpose of a quality audit includes all of the following except: A. Examines the work of the project and formally accepts the work results B. Determines how the project is progressing and makes corrections C. Identifies lessons learned D. Reviews quality management activities to ensure the right quality elements are being examined
What are the different software reengineering activities?
You are the project manager for a construction company that is building a new city and county office building in your city. You recently looked over the construction site to determine if the work to date was conforming to the requirements and quality standards. Which tool and technique of Quality Control are you using? A. Performance measurements B. Inspection C. Sampling D. Prevention
Your project got delayed by 40 days and you have to keep it back.what steps you would take.
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published the scope statement and the supporting detail. The supporting detail contains all of the following except: A. Constraints B. Other project information not noted in the scope statement C. Code of accounts D. Assumptions
Project managers spend what percentage of their prime communicating? A. 90 B. 85 C. 75 D. 50
The Project which is handled by you is in RED, customer has given you 4 weeks to show improvement, still nothing has worked out. The Customer again gives 3 weeks to improve and you do your best to improve, but nothing works out. Now the customer is not at all happy, HOW TO CONVINCE THIS CUSTOMER ???
8 Answers AZS, BGR Energy, Wipro,
You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.
You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and how the information should be stored and filed is which of the following? A. Scope management plan B. Communications management plan C. Information distribution plan D. Project charter
What are the outputs of the Performance Reporting process? A. Performance reports and change requests B. Performance reports and other project records C. Change requests and performance reporting D. Change requests and performance measurements
Which of the following describes the cost of quality associated with scrapping, rework, and downtime? A. Internal failure costs B. External failure costs C. Prevention costs D. Appraisal costs