You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following?
A. Achievement theory
B. Expectancy theory
C. Maslow's theory
D. Contingency theory


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

how many chart of a/cs can assign to company code?

1 Answers  


You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.

0 Answers  


You are a project manager for Laurel's theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. You know all of the following are true regarding Cost Control except: A. Performance is monitored to detect variances B. Changes are reflected in the cost baseline C. Changes are monitored and reflected in the project scope D. Changes are monitored so that inappropriate changes do not get into the cost baseline

0 Answers  


Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates

0 Answers  


You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are performing earned value analysis, trend analysis, and performance reviews. Which of the following is true? A. This is performance measurement documentation, which is an input to the Contract Closeout process B. This is performance measurement documentation, which is an input to the Administrative Closure process C. These are performance reporting tools and techniques of the Administrative Closure process D. These are performance reporting tools and techniques of the Contract Closeout process

0 Answers  






Which of the following is true regarding Administrative Closure? A. It occurs at the end of a project phase and at the end of the project. B. It occurs at the end of the project phase only. C. It occurs at the end of the project only. D. It is performed prior to Contract Closeout.

0 Answers  


You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram

0 Answers  


Your project is in the Scope Definition process. You've just completed the WBS. Which of the following is true? A. The WBS breaks the project deliverables down to a level where alternatives identification can be used to determine how level two assignments should be made. B. The WBS breaks the project deliverables down to a level where project constraints and assumptions can be easily identified. C. The WBS breaks the project deliverables down to the work package level where product analysis can be documented. D. The WBS breaks the project deliverables down to the work package level where cost and time estimates can be easily determined and quality control measurements can be determined.

0 Answers  


Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  


You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.

0 Answers  


You have been assigned to a project in which the objectives are to direct customer calls to an Interactive Voice Response system before being connected to a live agent. You are in charge of the media communications for this project. You report lo the project manager in charge of this project and the VP of marketing, who share responsibility for this project. Which organizational structure do you work in? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization

0 Answers  


Categories