You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You’re heading up a project to promote a new line of souvenirs to be sold at the shows. You need to gather the inputs to write the scope statement. You gather which of the following?
A. Project charter, product description, assumptions, and constraints
B. Project charter, product analysis, and cost benefit analysis
C. Product description, product analysis, and project charter
D. Product description, assumptions, constraints, and product analysis
No Answer is Posted For this Question
Be the First to Post Answer
PERT is: A. The longest path B. A weighted average technique C. A simulation technique D. Widely used in practice to determine schedule durations
You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. Resources are not readily available as they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project? A. Negotiation and influencing skills B. Communication and organizational skills C. Communication skills D. Problem-solving skills
You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A
All of the following are true about decomposition except: A. It's an output of the Scope Definition process. B. It's a tool and technique of the Scope Definition process. C. It is used to create a WBS. D. It subdivides the major deliverables into smaller components.
Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques
You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports
During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.
You are the project manager for Heartthrobs by the Numbers Dating Services. You're working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You've just completed your project staff assignments and published the project team directory. Which process are you in? A. Resource Planning B. Organizational Planning C. Project Development Planning D. Staff Acquisition
During which project management process are risk and stakeholder's ability to influence project outcomes the highest at the beginning of the process? A. Planning B. Executing C. Initiation D. Controlling
Your organization regularly uses a tool and technique of the Contract Closeout process to identify lessons learned, including the successes and failures, which will benefit future activity on this project and on future projects. Which tool and technique arc they using? A. Product documentation inspection B. Contract process review C. Performance measurement review D. Procurement audit
You are the project manager for Fun Days vacation packages. Your new project assignment is to head up the Fun Days resort opening in Austin, Texas. You are estimating the duration of the project plan activities, devising the project schedule, and monitoring and controlling deviations from the schedule. Which of the Project Management Knowledge Areas are you working in? A. Project Scope B. Project Quality C. Project Integration D. Project Time
You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.