Which of the following contracts should you use for projects that have a degree of uncertainty and require a large investment early in the project life cycle?
A. Fixed price
B. Cost reimbursable
C. Lump sum
D. Unit price


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization's operating system on 236 servers. You performed this project under contract. You are in the Contract Closeout process and know that you should document: A. Lessons learned B. Performance measurements C. Formal acceptance D. Product verification

0 Answers  


You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time

0 Answers  


What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

0 Answers  


You are a project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements, because the poles are not buried to the correct depth. Which of the following is true? A. You are in the Quality Assurance process and have performed a quality audit to assure correctness of work. B. You are in the Scope Verification process and have performed a quality audit to assure correctness of work. C. You are in the Contract Administration process and have completed a contract audit to assure the subcontractor's performance meets the contract requirements. D. You are in the Performance Reporting process and have completed a performance review of the contractor's work.

0 Answers  


Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project? A. The strategic plan, because you'll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is similar in nature. C. The product description, which would describe all the details of the run/walk program. D. Historical information from the recent blood drive project.

0 Answers  






As a PMP, one of your responsibilities is to ensure integrity on the project. When your personal interests are put above the interests of the project or when you use your influence to cause others to make decisions in your favor without regard for the project outcome, this is considered: A. Conflict of interest B. Using professional knowledge inappropriately C. Culturally unacceptable D. Personal conflict issue

0 Answers  


Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.

0 Answers  


What is the difference between contingency and mitigation plan?

1 Answers  


This measurement is the value of the work that's been completed to date: A. PV B. AC C. EV D. EAC

0 Answers  


The project charter: A. Includes a product description, describes the business need of the project, and is published by the project manager B. Includes a product description, describes the business need of the project, and is published by the project sponsor C. Includes the contract when the project is performed by a vendor and is published by a manager external to the project D. Includes a product description, describes the business need of the project, and is published by a manager external to the project

0 Answers  


PERT is: A. The longest path B. A weighted average technique C. A simulation technique D. Widely used in practice to determine schedule durations

0 Answers  


You are the project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a scope statement should be published prior to proceeding to the Planning processes. All of the following are true regarding scope statements except: A. It documents roles and responsibilities. B. It can be modified to reflect changes to the scope of the project. C. It describes the project deliverables, requirements, and objectives D. It serves as a baseline for future project decisions.

0 Answers  


Categories