You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true?
A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline.
B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against.
C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against.
D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following to identify the variables that will have the greatest effect on project outcomes? A. Design of experiments B. Bench marking C. Benefit/cost analysis D. Flow charting
You are a project manager working on contract with a company in a foreign country. At the project kick-off meeting, you are given an expensive-looking gift. The person who presented this to you said that it is customary in their country to give their business partners gifts. What is the most appropriate response? A. Thank them and decline. Explain that this is considered personal gain, which is unacceptable in your country. B. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. C. Thank them and decline. Explain that this is considered a conflict of interest, which is unacceptable in your country. D. Thank them and accept since you know that it would be considered offensive to decline the gift in their culture. Immediately report the acceptance of the gift to the appropriate parties at your company so that your actions are not called into question later.
What was the biggest challenge you faced in your project?
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What is the CPI of this project? A. 0.80 B. 1.25 C. 1.5 D. 0.83
The lowest level of the WBS is called what? A. Code of accounts B. Requirement C. Milestone D. Work package
Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find that during UAT, the system fails and is not working, how will u communicate to your customer, what solution will you provide to the client?
what kind of questions can be asked from SDLC for a project leader role?
What are the Scope Planning process tools and techniques? A. Benefit/cost analysis, work breakdown structure templates, expert judgment, and supporting detail B. Product analysis, benefit/cost analysis, alternatives identification, and expert judgment C. Product analysis, work breakdown structure templates, supporting detail, and expert judgment D. Benefit/cost analysis, alternatives identification, supporting detail, and expert judgment
All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance
The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals
What do you think you can bring to this position?
0 Answers Ross Stores, Starbucks,
The purpose of a quality audit includes all of the following except: A. Examines the work of the project and formally accepts the work results B. Determines how the project is progressing and makes corrections C. Identifies lessons learned D. Reviews quality management activities to ensure the right quality elements are being examined