You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true?
A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline.
B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against.
C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against.
D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

The tools and techniques of Source Selection include all of the following except: A. Contract negotiation B. Work authorization system C. Weighting systems D. Independent estimates

0 Answers  


What are the functions of project management tool?

0 Answers  


Which performance measurement tells us what the projected total cost of the project will be at completion? A. ETC B. CPI C. SPI D. EAC

0 Answers  


All of the following are true regarding the WBS except: A. It is a deliverables-oriented grouping of project deliverables and elements. B. It defines and organizes the work of the project in a hierarchical form. C. It provides a framework for the work of the project, and work not shown on the WBS is not included in the project. D. It defines all the deliverables of the project, but the activities level should not be listed on the WBS.

0 Answers  


You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are performing earned value analysis, trend analysis, and performance reviews. Which of the following is true? A. This is performance measurement documentation, which is an input to the Contract Closeout process B. This is performance measurement documentation, which is an input to the Administrative Closure process C. These are performance reporting tools and techniques of the Administrative Closure process D. These are performance reporting tools and techniques of the Contract Closeout process

0 Answers  






Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates

0 Answers  


Why do you want to switch over from IT to management?

0 Answers   EX,


Which of the following is true regarding constraints and assumptions? A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes. B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team. C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project teamwork within predefined budgets or time lines. D. Constraints and assumptions are inputs to the Initiation process. They should be documented, as they will be used throughout the project Planning process.

0 Answers  


Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning

0 Answers  


All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance

0 Answers  


All of the following describe the activity list except: A. It's an extension of the WBS. B. It includes all activities of the project. C. It describes the WBS updates. D. It includes a description of project activities.

0 Answers  


All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction

0 Answers  


Categories