If your expected value is ll0 and the standard deviation is l2, which of the following is true?
A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days.
B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days.
C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days.
D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.
No Answer is Posted For this Question
Be the First to Post Answer
What are the five project management process groups, in order? A. Initiation, Executing, Planning, Controlling, and Closing B. Initiation, Controlling, Planning, Executing, and Closing C. Initiation, Planning, Controlling, Executing, and Closing D. Initiation, Planning, Executing, Controlling, and Closing
Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start
What is triple constraint triangle in project management?
All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT
This process applies evaluation criteria to the bids and proposals received from potential vendors: A. Solicitation B. Contract Administration C. Source Selection D. Quality Assurance
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What do you know about this project? A. The EAC is a positive number, which means the project will finish under budget. B. You do not have enough information to calculate CPI. C. The CV is a negative number in this case, which means you've spent less than what you planned as of the measurement date. D. The CV is a positive number in this case, which means you're under budget as of the measurement date.
You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.
Brainstorming and the Delphi technique are two types of information-gathering techniques found in which process? A. Risk Management Planning B. Risk Response Control C. Risk Identification D. Quantitative Risk Analysis
Project selection criteria might include: A. Benefit measurement methods B. Constrained optimization analysis C. NPV calculations D. Potential market share or increased public perception
You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic
All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.
Write about organising and staffing in management.
0 Answers Mahatma Gandhi University,