You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend?
A. Project A because the cost to implement is cheaper than Project B
B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B
C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A
D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A
No Answer is Posted For this Question
Be the First to Post Answer
you are the project manager of a project , customer is asking for a change in scope and agrees that it will be a CR. But you do not want to take the CR for whatever reason. How will you convince the customer in doing so
Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.
What is your leadership style?
1 Answers State Bank Of India SBI,
You are in the Planning process of your project, and your project sponsor has requested an accurate cost estimate in two weeks from today. You'll use which of the following techniques to provide her with the most accurate cost estimate? A. Bottom-up B. Analogous C. Top-down D. Earned value
You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away. Which of the following is true? A. This project ended due to extinction because it was completed and accepted. B. This project ended due to integration because it was completed and accepted and the project manager moved on to a new project. C. This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films. D. This project ended due to integration because it was completed and accepted.
what do you do after a milestone is completed?
Your project was just completed. Due to some unfortunate circumstances, the project was delayed causing cost overruns at the end of the project. Which of the following is true? A. You document the circumstances as lessons learned. B. You pay particular attention to archiving the financial records for this project. C. Your project ended due to starvation because of the cost overruns. D. You document the circumstances surrounding the project completion during the Scope Verification process.
Intellectual property includes all of the following except: A. Software B. Patents C. Hardware D. Business processes
Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find that during UAT, the system fails and is not working, how will u communicate to your customer, what solution will you provide to the client?
What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action
You are the project manager for Insomniacs International. Since you don't sleep much, you get a lot of project work done. You're considering recommending a project that costs $575,000, and expected inflows are $25,000 per quarter for the first 2 years, and then $75,000 per quarter thereafter. What is the payback period? A. 40 months B. 38 months C. 39 months D. 41 months
The Project which is handled by you is in RED, customer has given you 4 weeks to show improvement, still nothing has worked out. The Customer again gives 3 weeks to improve and you do your best to improve, but nothing works out. Now the customer is not at all happy, HOW TO CONVINCE THIS CUSTOMER ???
8 Answers AZS, BGR Energy, Wipro,