You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away. Which of the following is true?
A. This project ended due to extinction because it was completed and accepted.
B. This project ended due to integration because it was completed and accepted and the project manager moved on to a new project.
C. This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films.
D. This project ended due to integration because it was completed and accepted.
No Answer is Posted For this Question
Be the First to Post Answer
what is a project management?
16 Answers Areva, GB Engineering, Proteans,
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What is the CPI of this project? A. 0.80 B. 1.25 C. 1.5 D. 0.83
You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833
What is the meaning of scope of the project?
You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite sometime and are in the performing stage of Team Development. A new member has been introduced to the team. Which of the following is true? A. The Team Development process will start all over again with the storming stage. B. The team will continue in the performing stage. C. The Team Development process will start all over again with the forming stage. D. The team will start all over again at the storming stage but quickly progress to the performing stage. ?
You are project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a project charter should be published prior to proceeding to the Planning processes. All of the following are true regarding project charters except: A. Project charters always include cost and time estimates. B. Project charters always include the product description and business need for the product. C. Project charters recognize and acknowledge the existence of the project. D. Project charters commit organizational resources to the project.
Project selection criteria might include: A. Benefit measurement methods B. Constrained optimization analysis C. NPV calculations D. Potential market share or increased public perception
You are the project manager for a new construction project in your city. Your longtime personal friend is bidding on the project. They've asked you to give them an indication of the budget for this project so that they do not overbid and lose the deal. What is the most appropriate response? A. Give the information to your friend. You know their character and can trust that they won't tell anyone. B. Tell your friend that after all this time, they should know you better than to think you'd put your personal integrity on the line or compromise your job due to a conflict of interest. Decline to give them the information. C. Tell your friend you'll give them the information if they'll promise not to tell anyone and if they'll agree to help you out with some materials on your basement-refinishing project. D. Give the information to your friend and inform the project sponsor so that the information can be shared with the other bidders as well.
how to handle project single handed?and what are the roles and responsibilities of a project leader?
The Project Management Knowledge Areas: A. Include Initiation, Planning, Executing, Controlling, and Closing B. Consist of nine different areas that bring together processes that have things in common C. Consist of five different processes that bring together phases of projects that have things in common D. Include Planning, Executing, and Controlling processes as these three processes are commonly interlinked
What is one of the advantages of a functional structure? A. All employees report to one manager and have a clear chain of command. B. All employees report to two or more managers, but project team members show loyalty to functional managers. C. The organization is focused on projects and project work. D. Teams are collocated.
All of the following are characteristics of the project Closing processes except: A. Probability for success is greatest here. B. The project manager's influence is greatest here. C. The stakeholders' influence is least here. D. Risk is greatest here.