During a review of a business continuity plan, an IS auditor noticed that the point at which a situation is declared to be a crisis has not been defined. The MAJOR risk associated with this is that:

A. assessment of the situation may be delayed.

B. execution of the disaster recovery plan could be impacted.

C. notification of the teams might not occur.

D. potential crisis recognition might be delayed.



During a review of a business continuity plan, an IS auditor noticed that the point at which a situa..

Answer / chatter

The correct answer is B

A. Problem and severity assessment would provide information necessary in declaring a disaster, but the lack of a crisis declaration point would not delay the assessment.

B. Execution of the business continuity and disaster recovery plans would be impacted if the organization does not know when to declare a crisis.

C. After a potential crisis is recognized, the teams responsible for crisis management need to be notified. Delaying the declaration of a disaster would impact or negate the effect of having response teams, but this is only one part of the larger impact.

D. Potential crisis recognition is the first step in recognizing or responding to a disaster and would occur prior to the declaration of a disaster.

Question #: 253 CISA Job Practice Task Statement: 2.10

Is This Answer Correct ?    3 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

An IS auditor reviewing an outsourcing contract of IT facilities would expect it to define the: A. hardware configuration. B. access control software. C. ownership of intellectual property. D. application development methodology.

1 Answers  


The MOST significant level of effort for business continuity planning (BCP) generally is required during the: A. testing stage. B. evaluation stage. C. maintenance stage. D. early stages of planning.

2 Answers  


The use of residual biometric information to gain unauthorized access is an example of which of the following attacks? A. Replay B. Brute force C. Cryptographic D. Mimic

1 Answers  


Which of the following procedures should be implemented to help ensure the completeness of inbound transactions via electronic data interchange (EDI)? A. Segment counts built into the transaction set trailer B. A log of the number of messages received, periodically verified with the transaction originator C. An electronic audit trail for accountability and tracking D. Matching acknowledgement transactions received to the log of EDI messages sent

2 Answers  


The editing/validation of data entered at a remote site would be performed MOST effectively at the: A. central processing site after running the application system. B. central processing site during the running of the application system. C. remote processing site after transmission to the central processing site. D. remote processing site prior to transmission of the data to the central processing site.

1 Answers  






A company performs full backup of data and programs on a regular basis. The primary purpose of this practice is to: A. maintain data integrity in the applications. B. restore application processing after a disruption. C. prevent unauthorized changes to programs and data. D. ensure recovery of data processing in case of a disaster.

2 Answers  


To check the performance of flow and error control, an IS auditor should focus the use of a protocol analyzer on which of the following layers? A. Network B. Transport C. Data link D. Application

2 Answers  


During an audit of a telecommunications system the IS auditor finds that the risk of intercepting data transmitted to and from remote sites is very high. The MOST effective control for reducing this exposure is: A. encryption. B. callback modems. C. message authentication. D. dedicated leased lines.

2 Answers  


The responsibilities of a disaster recovery relocation team include: A. obtaining, packaging and shipping media and records to the recovery facilities, as well as establishing and overseeing an offsite storage schedule. B. locating a recovery site if one has not been predetermined and coordinating the transport of company employees to the recovery site. C. managing the relocation project and conducting a more detailed assessment of the damage to the facilities and equipment. D. coordinating the process of moving from the hot site to a new location or to the restored original location.

1 Answers  


Which of the following is the PRIMARY reason for involving an IS auditor in the definition of a system's requirements? A. Post-application reviews do not need to be performed. B. Total budgeted system development costs can be reduced. C. It is costly to institute controls after a system becomes operational. D. The extent of user involvement in design activities is reduced.

1 Answers  


Which of these has the potential to improve security incident response processes? A. Review the incident response procedures. B. Post-mortem or post-event reviews by the security team. C. Getting the hot-site ready. D. Reviw the BCP plan every six months

1 Answers  


While copying files from a floppy disk a user introduced a virus into the network. Which of the following would MOST effectively detect the existence of the virus? A: A. scan of all floppy disks before use B. virus monitor on the network file server C. scheduled daily scan of all network drives D. virus monitor on the user's personal computer

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)