How can i calculate the amount cement, steel , sand nd aggregate reguired for 1000 sq ft of r.c.c?
Answers were Sorted based on User's Feedback
Answer / utpal
first of you decide the depth of concreting work & use grade of concrete and fe fo steel grade and after that calculation of all this quentity
for example of 1 cum concereting work that means 1m x 1 m x 1m so that
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag
Is This Answer Correct ? | 1 Yes | 0 No |
Which code is used for tor & tmt steel bar?
Explain the different types of roofing systems?
what is the proper procedure in conducting a california bearing ratio penetration test on soil on cbr machine?
Do you expect there to be many jobs for civil engineers going into the future? What are the three main drawbacks of being a civil engineer? What are the three best things about being a Civil engineer? What amount of vacation time is available to you? Is the time paid? What are the usual hours of work required? Is it possible, or common, to work from home? How much time do you spend on the site of your projects? What type of schooling is required to be a civil engineer? How many years are required to complete this education?
What is minimum tensile strength required for structural steel works ?
what is the procedure to make compressive strength test for concrete cube in lab
how much quantity of cement and sand required for construction of 10 cum brick work( Brick size 3"*4"*9"(Standard size ) an d for 10 cum construction of SSM (Size stone masonary) with Cm 1:6 for both.
11 Answers GRC, KEC, L&T, Techno Electric and Engineering, UPENN,
Is there a way to know the aprox shuttering qty if vol of concrete is known? any thumb rule?
why we use aggregate,sand with cement in concrete?
In case of tunnels (Railway) what is the way of securing a wall beam?
Diagonal check is required for a layout work to confirm ––
What do mean by freeway ?