How can i calculate the amount cement, steel , sand nd aggregate reguired for 1000 sq ft of r.c.c?
Answer Posted / utpal
first of you decide the depth of concreting work & use grade of concrete and fe fo steel grade and after that calculation of all this quentity
for example of 1 cum concereting work that means 1m x 1 m x 1m so that
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag
| Is This Answer Correct ? | 1 Yes | 0 No |
Post New Answer View All Answers
difference between fc and fc'?
A 16 pile group, consisting of diameter concrete piles, were cast in situ in a clayey soil whose unconfined compressive strength is 1100 psf. Each pile is 60 ft long and the pile spacing is 2.5 times the pile diameter.The water table is at the ground surface and saturated unit weight of the clay is 118 lb/cu.ft. using a factor of safety 3 and a reduction factor =0.45, compute the allowable capacity of the piles acting as individuals
How many feet are in 4 square yards?
1) write Short notes about Shellow & Deep well? 2) What is the full form of SPT & SMB? write short notes. 3) write short notes about efficiency of Riveted joint.
how to calculate total cost for slab 35'×8'
Which are the top apps for you civil engineering?
how can calculate the compressive strength of concrete cylinder by water cement ratio ?
Aptitude, reasoning, quants, verbal and technical question
WHAT R THE GENERAL TECH QUESTIONS ASKED FOR THE INTERVIEW FOR AN AUTOMOBILE INDUSTRY,SPECIALLY DESIGN DEPT
CAN V USE CRUSH SAND FOR CLAY BRICK MASONARY
how to calculate cut length of re-bar in a circle . because we not place same length of re-bar in whole circle maximum in center and minimum at corner so how to calculate middle bars???
What is the origin of name railway sleepers?
In how many types u can do POP on ceiling and walls(on which material or by using which material)? b) what is the difference between dry , oil bound, enamel, acrlyic type of painting? 2nd :- I have certain queries, please help to solve. a) length of pile bore is 4m.excavation quantity will be area * length where area will be pi/4 * dia*dia. Is this right? b) It is a single reamed pile of 300m dia and reamed dia is 750mm. can any body help me to calculate excavated quantity of this bulb(reamed section),, concrete quantity in bulb with showing the formulas to be used?
Difference between lime, distemper and plastic emulsion?
how to tie 10 legged stirrups