Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

How can i calculate the amount cement, steel , sand nd aggregate reguired for 1000 sq ft of r.c.c?

Answer Posted / utpal

first of you decide the depth of concreting work & use grade of concrete and fe fo steel grade and after that calculation of all this quentity
for example of 1 cum concereting work that means 1m x 1 m x 1m so that
M20 = 1:1.5:3
Volume = 1+1.5+3=5.5
Total volume ingredients for using =1.57
Volume of broken stone Require = (3/5.5) x 1.57 = 0.856 m3
Volume of sand Require = (1.5/5.5) x 1.57 = 0.471 m3
Volume of cement = (1/5.5) x 1.57 = 0.285 m3
= 0.285 x1440 = 411 kg
For 1m3 of M20 (1:1.5:3)
Broken stone = 0.856 m3
Sand = 0.472 m3
Cement = 8.22 bag

Is This Answer Correct ?    1 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Please let me know what is the simplest way of Calculating Mix Designs

2000


How do you calculate the unit weight of concrete?

1122


How much cement and sand required for 9"brick wall per square metre

2911


what is that one cub metre plaster in cemant and fine sand

2037


How much material will consume for following specification water tank (9*7.5*6 feet)?

2075


what is c4x light weight cement blocks

5654


How to come 1.54 from dry to wet concrete? 

2256


What is the number of IS code of practice to be followed for hydraulic design of sewerage pipe line?

2621


Which are the top apps for you civil engineering?

1138


how to absorb to site basic corrections? which are the important correction?

1469


What in your past experience or education prepares you for the position for which you are applying

2207


five benefits of using standard terminology in the measurement process

3428


HOW MANY BAGS OF CEMEMT USED IN PER M2 OF PARTITION WALL

1449


cement required for construction of 400mm*200mm*200mm concrete solid blocks for 1sq.mtrs,how?

2379


PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg

2335