In barbending schedule why is o.42*D is taken. Means why o.42 only???

Answer Posted / arghya das

that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is the sugested procedure of water purification for public supply?

1723


i) Distinguish between Theodolite and dumpy Level? (Marks-8) ii)Distinguish between Viscous and Turbulent flow? (Marks-8) iii) Distinguish between nominal and design mix? iv) What is standard sand? v) Explain the term plane stress? Vi) Differentiate between principal plane and principal axis? Vii) write short notes on Elastic limit of structural steel? viii) Write short notes on stress concentration? ix) write short notes on "Grading of Sand" ? x) How many grades of concrete are there under standard concrete?

11539


What is the difference between one-way slab and two-way slab?

670


Civil engineering material testing Standard results

1876


how beam.coloum ,slab, footing are designed as per indian code.. detail procedure?

2137






How much form and scaffolding per cubic meter volume of concrete class ''A'', ''B'', and ''C''

1651


What is a tensile strength? What is the tensile strength of wood?

680


how do we calculate quantity of cement sand and aggregates in 1m3 of m20 m25 grade concrete?

2004


what is floating slab foundation?

676


What is the use of mirror command?

770


how i can tak Quantity of mortar in block work

1988


what is grade intersection?

1612


What in your opinion makes you the most suitably qualified candidate for this post of civil engineering technician?

703


what does the track parameter mean in staad.pro?

5473


How to calculate material and labor required for 100 m2 plaster?

1253