In barbending schedule why is o.42*D is taken. Means why o.42 only???
Answer Posted / arghya das
that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.
| Is This Answer Correct ? | 4 Yes | 0 No |
Post New Answer View All Answers
Explain why concrete barriers have curved surface profiles?
How much area, in square meters, will one liter of paint cover if it is brushed out to uniform thickness of 600 microns?
100mm block work 64 bags of cement used 150mm block work 286 bags of cement used 200mm block work 20 bags of cement used patly work (M15) 293 bags of cement used mortar ratio is 1:5 how to calculate volume of sand in cum & no. of bags
What are the advantages of cad software?
What is standard Sand? What is Regime condition? What do you mean by the core trench in Earthen Dasm? What is soundness test for cement? When negetive shear force takes place in a R.C.C member?
Why are steel plates inserted inside bearings in elastomeric bearing?
Explain how you can use different dimension tools in CAD? What are the different dimensions available?
how can can column be corrected when the design is not safe ? is the increasing the clearcover a solution?
What is the difference between Hinged and pinned in Column ends
If a slab concrete is placed with M-20 grade concrete, actually it has to be placed with M-30. what are the rectifications / measures to be taken after concreting is done.
What is the cost of shuttering per Sqm.? How it is calculate by thumb rule...?
What are the govt approvals required for starting of power project. means from initial site grading and excavation work.exm. blasting in hard rock, deep excavation, cut off trees from site.
when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?
What difference comes in constructing of house and a housing complex like society
what is the permanent solution applied for restoration of leaning tower of pisa?