In barbending schedule why is o.42*D is taken. Means why o.42 only???

Answer Posted / arghya das

that is 1.42d-d=0.42d
(1.42d comes from 1/sin45) 45 degree crank bar.

Is This Answer Correct ?    4 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Explain what is Critical Path Method (C.P.M)?

769


what radial pressure, the NP2 class rcc pipe can sustain?

2988


what is flashing?

809


how we calculate the grade of the Bituminous materials.?????

1942


what should be RCC material i.e iron rod(mm)x cement x stone x sand for laying of slab L 42'x B 22'x tk 0.375ft = 1nos & column of H 17'x15"x8" 2nos.

2008






What do you mean by tolerance factor of concrete ?

2764


Explain major difference between auto level and dumpy level?

853


according to the painting co efficient, we should take the one side of doors (or) windows or both sides?

1386


how to preaper for interview wat they asked in interview give me idea

2275


How do you compute moisture correction using the parameters gathered from Nuclear Density Gauge Apparatus and the moisture contents results from the lab.?

1896


Please let me know what is the simplest way of Calculating Mix Designs

1638


what are the cube & Sylinder strength of concret M20,M25,M30,M35,M40,M60 ,M75,M10 ,M15

2614


How can we convert weight batch to volume batch for m30 mix

2551


when reinforcement binding completed if there is more cover than the required what is the solution to reduce the cover?

1816


for 200 kg of cement how is the mix proportion in kg for m25 grade of concrete

1580