How many binding wire is use in arrangement of 25mt steel
Answers were Sorted based on User's Feedback
Answer / shweta garg
in steel reinforcement binding wire required is 8kg per MT, so for 25MT the binding wire required is 25*8= 200kg
| Is This Answer Correct ? | 11 Yes | 1 No |
how much should we assume for the weight of foundation ??
Is the ratio fixed for M-20,M-25,M-30,M-35....grades of concrete??
2 Answers Ahluwalia Contracts, L&T,
Explain the advantages and disadvantages of using plastic and timber fenders?
What are the structural steel & where they are used
que.is ideal size of bricnk use in india,joint size of mortar in massinary ,how many bricks used in 1cum.how to test at site.what is the possition of marka used in bricks?
In barbending schedule why is o.42*D is taken. Means why o.42 only???
what"s the formula to find the cement,sand,aggreegate(45mm) requirement for PCC?
how to calculate detail quantity of bricks and mortar for 500 cu.ft masonry work. consider wall thickness 9 inches
Why we provide hair pin for shed
how much grade of concrete can be used for different structural element such as slab,beam,column,footing & plinth beams? and type of cement can be used in construction work & also types of cemnt grades
what is project?
Whta is the proportion of M30
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)