How many binding wire is use in arrangement of 25mt steel
Answer Posted / shweta garg
in steel reinforcement binding wire required is 8kg per MT, so for 25MT the binding wire required is 25*8= 200kg
Is This Answer Correct ? | 11 Yes | 1 No |
Post New Answer View All Answers
what is the method used for marking of cantilevers in hirise buildings by using theodolite
How you can use different dimension tools in cad? What are the different dimensions available?
I am a civil engineering student and going to attend interview in this week in an IT company.Will they ask me questions about my area of interest or cs
I need model question papers for writing the Dubai municipality exam,for G+1
RR masonry rate analysis
asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream
How to calculate construction cost of residential building in mumbai
how much shouid be the rate for ready mix concrete per cubic meter
what is the painting co efficient of slope roof tiles?
What is the yield of 100 litres of water and 10 kg of cement in grout mix?
what motivates you to do a good job
What is the difference between the concrete mix design carried out by IS10262 and by ACI method ?
1) a)to prepare mortar for bricklaying how much amount of water should be added for its maximum strength and workability(to avoid cracks which results, when high quantity of water is added)?is their a formula or ratio? b) suppose we want to make 1:3 mortar,what is the best way to measure cement ,sand and water and how? c)time before which freshly prepared mortar should be used? d)proper way to mix and make mortar? e)when should curing start after laying bricks and for how long?and also how many hours per day? f)what is shear wall (please in terms of layman lol) bookish definisions are confusing.... g) and last,acc to codes what are max no. of course that should be laid in a day.
The portion of a brick cut across the width is called?
Why should pumping be not used in case of concreting works?