How gate result to cube for 7 day?
Formula for the cube testing?
Answer / ajmal khan
Days
--------------- X Fck
4.7+ 0.833 days
For Example M20 =
7
--------------- X 20
4.7+ 0.833*7
= 13.29N/sqmm. Aproximately 1/3rd of 20N.
We can find for any day of any grade.
| Is This Answer Correct ? | 6 Yes | 1 No |
What is the cement and sand consuption of 1:4 block work
Rate analysis of Vitrified tile in cement mortor 1:3
0 Answers Design Space, Muthoot Group,
what is called camber in the road ?
writte a c prog. to acept 5 no. from consule and then display them back on consulte in ascending order
How much area can plaster with one bag of cement?what is the size of the fuji blocks?
what is C50 expressed in kg/m3
How to calculate the area in squarefeets ?How much area of sqft for this measurements?East 53.3ft West 54ft North 47.7ft South 51.1ft ?
how we calculate the vol.of wet concrete..?
How to provide spacer bar in barbending work,parallel to bar or inclined to bar? What is the reason?
if a pipe those configuration (ASTM c 76 class b 450mm dia 2500mm length) fixing for water course those lining of water is 7000 running meter. my question is that if 8 joints of pipe ls leakage and we have not permission to stop the water so which treatment we apply on joint in that in condition.
How can I calculate the Compressive strength of cubes after 28 days of curing?Is there any formula or ration ?
Define What is a projection line?
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)