How much actual % of wastage of steel...

Answer / deoghar

3 %

Is This Answer Correct ?    8 Yes 2 No

How much actual % of wastage of steel...

Answer / haider

2%

Is This Answer Correct ?    1 Yes 0 No

How much actual % of wastage of steel...

Answer / kumars

Mostly 3-4% For Procurement, Actual around 3% , But Depends on Design,

Is This Answer Correct ?    1 Yes 1 No

How much actual % of wastage of steel...

Answer / dileep naik

Its depend upon Design & use of bars.
generally considered 3%

Is This Answer Correct ?    0 Yes 1 No

How much actual % of wastage of steel...

Answer / ajaysenapati

More than 5%

Is This Answer Correct ?    0 Yes 2 No

Post New Answer

More Civil Engineering Interview Questions

Project at andheri west mumbai total area of 116000 sq ft near by..Please help me out for quotation plan is ready basic details are with me , please help me out .I will mail u in autocad also.

1 Answers   AK Construction,


what is the full form of GGBS?

2 Answers   UltraTech,


please what are the required bars for a beams of 6mx6m and 450x300mm, one is continuous and the the second is discontinuous ..Its a commercial building (church)

0 Answers  


Brick size 230X115X150mm, how many bricks, quantity of sand, cement required to construct 10 sq mtrs of 115mm thick brick wall.

3 Answers   Feana,


Rate analysis of Vitrified tile in cement mortor 1:3

0 Answers   Design Space, Muthoot Group,






what is the difference between TOR & TMT

1 Answers   Wonderla Holidays,


how to calculate no of rings & weight of column including rings?

2 Answers   HCC, Shivam Constructions,


how many cement bag in 1m*m*m

33 Answers  


As a proof of my analytical skills I was asked to give an example of a real life situation that i have solved analytically ? Can anybody give me a clue what kind of examples should be a suitable answer ?

0 Answers   Infosys,


for a column of size 400*230mm column reinforcement= 8-20x(cant write the symbol,i hope u guys undersstand,something like (fi) column stirups=8x@(4l) 230c/c 1)what does these mean 2)how to calculate quantity of steel for this column(ceiling height 11 ft)

0 Answers  


1.why can't we used sea sand in construction? 2.can we change sea sand into normal sand? if yes how?

2 Answers  


PLS.......... ANY ONE CAN FORWARD ME PREVIOUS QUESTION PAPER hpcl civil engg

0 Answers   HPCL,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5085)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4451)
  • Electrical Engineering Interview Questions Electrical Engineering (16632)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)