What is the amount of cement,sand and course aggregate(jully)(in kgs) required for the RCC of an area of 450 square feet and 5 inch depth if the concrete mixing ratio is 1:2:4(cement:sand:jully)?your answer will be very helpful.
Answer / mohd zubairali
first converted into meters we get 5.311 cum the ratio is (1:2:4)
0.92*1440/4=331.2kg/cum
cement is 331.2*5.311= 1759 kg
1759/50 = 35.1=36 BAGS of cemnt
.46*5.311=2.443CUM of sand
.92*5.311= 4.886CUM of aggregate
NOTE:-ONE CUM OF concrete IS 0.46cum of sand.
ONE CUM OF CONCRETE IS 0.92 CUM OF AGGREGATE
Is This Answer Correct ? | 0 Yes | 1 No |
types of piles?
if we use 1.25 bag of cement 3 pharma metal and 2 pharma crush sand what is the strenghtexpected for RCC column
percentage of wastage limits in construction materials EX : min & max . cement = fine aggregate = coarse aggregate = admixture = wood = tiles = painting = marbles = bricks =
how many plastr work in one bag cement
1:6 ratio block work purpose how much cement used
1 Answers Spago, VRC Constructions,
What do you mean by bond? What are the different types of bonds?
how to estimate costing from quantity givin in BOQ and according to this how we fill tender and final rate for perticular work.....?
How to hide dimensions in autocad?
what might be the problem faced in the near future if the M-sand is used in the place of river sand during wall plastering? (As per IS)
What is componsation
0 Answers Nagarjuna Construction,
what are the criteria for choosing the span for the bridge (highway bridge)
Can anyone tell me the salary and job profile of transportation engineers/transport engineer?