L&T APFC Relay model etacon L8 fault:
Initial power factor is 0.6
when capacitor is on, the value of power is getting down,
please let me know the reason and rectification details.
Answer / ramesh
L&T make etaCON L8 CAPACITOR BANK plant running time pf ok, plant shutdown time using 50nos tube light load pf 0.257,The capacitor bank not in service, programme procedure connect capacitor 5kvr
| Is This Answer Correct ? | 8 Yes | 0 No |
1 what is 5P00F METHOD IN 8085 MIC. PRO. 2 what is NEXT STATE FUNCTION SYNTHESIS 3 HOW THE MULTI LEVEL FAULT CAN BE DETECTED
SIR VERY GOOD MORNING I AM APPERING FOR RRB EXAM FOR SECTION ENGINEER I REQUEST U TO PLZ FORWORD THE PAPER PATTERN AND EVEN PREVIOUS QUESTION PAPER SIR. I THINK U WILL SURELY HELP ME OUT IN EXAM.
Explain why an ammeter should be of very low resistance?
please somebody who have asked questions related to electronic and communication eng siemens 2010-2012 post here
Explain why we are using the bridge rectifier in most of the circuits instead of full wave rectifier even though the output of both are same?
how many types of storage classes in c and embedded c
what is side band theory
Explain About RRC states?
Can anyone plzzz tel me how can we generate sinusoidal waveform using 8085 chip??????? plzz reply with corresponding assembly language program........or simply the accurate logic.....
what is the use of choke and starter in the tubelight?
What is instrumentation amplifier (ia) and what are all the advantages?
What losses occur in a thyristor during working conditions?
Civil Engineering (5086)
Mechanical Engineering (4453)
Electrical Engineering (16638)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)