For 25mm thick plastering how much sand and cement is used for 1 sft
Answer / karthik rajendren
For 10 Sqm = 10*.025=.25M3
Assume 25% Dry Mortor =0.25*1.25=0.3125
30% Wastages =0.3125*1.3=0.40625/10
For 1 Sqm =0.040625 M3
For CM 1:4,Cement
= 0.040625/5*28.8
=0.234Bags/m2
=0.234/10.764
=0.0217Bags/Sft
Sand=0.0217*0.035*4
=0.0031M3/Sft
Is This Answer Correct ? | 4 Yes | 2 No |
comparision difference between GSB and WBM subbase in road construction
GIVE US YOUR FULL DETAIL OF THE FOLLOWING… FULL NAME.. PERMENENT MAILING ADDRESS DIRECT CONTACT NO E MAIL ADDRES.
What is specific gravity & how it is calculated
What is design life of a bridge?
how to calculate column load bearing? how many weight capacity in 1m3 concrete? pls answere me sir.
What are the advantages of cad software’s?
Why we add salt in silt content test of sand? Full reason ?
what is mc arther pile?
what is the process of repair the structure in whitch reinforcement is open
How many types of traps are used?
How to Calculate the amount of Cement mortor required only for 12 or 10 mm bonding? I mean to know only the amount of mortar for bonding not for plastering. Help me to find this.
what is the lap length for pile reinforcement cage in water piling