Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


1.(a.) how do you calculate the volume of mortar for 1
piece of block 450mm x 225mm x 225mm.
(b.) calculate for 1sqm



1.(a.) how do you calculate the volume of mortar for 1 piece of block 450mm x 225mm x 225mm. (b.)..

Answer / karthik rajendren

Volume of 1 block without mortor =
0.45*0.225*0.225=0.0228m3/Nos
Volume of 1 block with 10mm thk mortor =
0.47*0.245*0.225=0.0259m3/Nos
So,Vol/Nos =0.0228-.0259=0.0031 m3/No.
For 1 Sqm = .0031*12.5=0.0388 m3/m2

Is This Answer Correct ?    4 Yes 3 No

Post New Answer

More Civil Engineering Interview Questions

For 1:2:4 ratio the weight of cement is 50 kgs then how many kgs are the weight of sand and aggregate

4 Answers   Lanco, Reliance,


What is mean by ITP in a construction project

6 Answers  


what is spacing of wallar support of 3m column. the thickness of column is 0.25 m.

0 Answers   Gammon,


What is passive earth pressure ?

0 Answers  


it is possiblee to produce concrete with out cracks...

0 Answers  


How to identify the vitrified tile and ceramic tile by observation only after executing the job.

0 Answers  


what is mean by bulking of sand?

11 Answers   CCCL, Kanakia Group,


HOw much % of premium on DSR-2013 currently

0 Answers   NICE,


DESIGN PROCEDURE OF THE COLUMNS

0 Answers   TCE,


I need to constructive work in amaraj batteries

0 Answers   Amara Raja,


practically where this hinge and roller condition used

2 Answers  


1.How much batten required for 1 sqm Shuttering. 2.how much pipe & clamps required for staging of 100 sqm shuttering at 5.0 m height.

0 Answers   NA,


Categories
  • Civil Engineering Interview Questions Civil Engineering (5086)
  • Mechanical Engineering Interview Questions Mechanical Engineering (4456)
  • Electrical Engineering Interview Questions Electrical Engineering (16639)
  • Electronics Communications Interview Questions Electronics Communications (3918)
  • Chemical Engineering Interview Questions Chemical Engineering (1095)
  • Aeronautical Engineering Interview Questions Aeronautical Engineering (239)
  • Bio Engineering Interview Questions Bio Engineering (96)
  • Metallurgy Interview Questions Metallurgy (361)
  • Industrial Engineering Interview Questions Industrial Engineering (259)
  • Instrumentation Interview Questions Instrumentation (3014)
  • Automobile Engineering Interview Questions Automobile Engineering (332)
  • Mechatronics Engineering Interview Questions Mechatronics Engineering (97)
  • Marine Engineering Interview Questions Marine Engineering (124)
  • Power Plant Engineering Interview Questions Power Plant Engineering (172)
  • Textile Engineering Interview Questions Textile Engineering (575)
  • Production Engineering Interview Questions Production Engineering (25)
  • Satellite Systems Engineering Interview Questions Satellite Systems Engineering (106)
  • Engineering AllOther Interview Questions Engineering AllOther (1379)