What is the difference between contingency and mitigation
plan?
Answer / ritesh singhal
What is Risk Mitigation?
Mitigation is the process of solving problems that were caused or reducing the effect of the risk once it arises. In other words, risk mitigation strives to minimize a risk that materializes. Risk mitigation can also be seen as a method used to control damage that has already being done, and to reduce the ‘blow’ or consequences that it may have on the organization.
What is Contingency ?
Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes. A contingency plan is also known as the action plan for the worst case scenario. Such plans are essential to an organization as it helps organization quickly adapt to changes while suffering less consequences.
Mitigation vs Contingency
• Risk management is essential for organizations to ensure the long term smooth running of the business. There are two parts to risk management; risk mitigation and contingency planning.
• Mitigation is the process of solving the problems that were caused or reducing the effect of the risk once it arises.
• Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes.
• Risk mitigation is aimed at reducing the consequences of the crisis, whereas contingency planning is used to determine how problems can be solved if a crisis occurs.
| Is This Answer Correct ? | 5 Yes | 1 No |
You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75
You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic
You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.
Explain the meaning of management.
0 Answers Mahatma Gandhi University,
Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.
The tools and techniques of the Source Selection process include all of the following except: A. Contract negotiation B. Correspondence C. Independent estimates D. Screening system
What are the 10 knowledge areas of project management?
Which performance measurement tells us how much more of the budget is required to finish the project? A. ETC B. EV C. AC D. EAC
If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.
Intellectual property includes all of the following except: A. Software B. Patents C. Hardware D. Business processes
How do you ensure that your project is always on track?
The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates