What is the difference between contingency and mitigation
plan?

Answer Posted / ritesh singhal

What is Risk Mitigation?
Mitigation is the process of solving problems that were caused or reducing the effect of the risk once it arises. In other words, risk mitigation strives to minimize a risk that materializes. Risk mitigation can also be seen as a method used to control damage that has already being done, and to reduce the ‘blow’ or consequences that it may have on the organization.

What is Contingency ?
Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes. A contingency plan is also known as the action plan for the worst case scenario. Such plans are essential to an organization as it helps organization quickly adapt to changes while suffering less consequences.

Mitigation vs Contingency

• Risk management is essential for organizations to ensure the long term smooth running of the business. There are two parts to risk management; risk mitigation and contingency planning.
• Mitigation is the process of solving the problems that were caused or reducing the effect of the risk once it arises.
• Contingency is a planning process in which the company will come up with a few backup plans in the event that the risk materializes.
• Risk mitigation is aimed at reducing the consequences of the crisis, whereas contingency planning is used to determine how problems can be solved if a crisis occurs.

Is This Answer Correct ?    5 Yes 1 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

Describe function-oriented metrics.

528


The Project Management Knowledge Areas: A. Include Initiation, Planning, Executing, Controlling, and Closing B. Consist of nine different areas that bring together processes that have things in common C. Consist of five different processes that bring together phases of projects that have things in common D. Include Planning, Executing, and Controlling processes as these three processes are commonly interlinked

1776


Your organization regularly uses a tool and technique of the Contract Closeout process to identify lessons learned, including the successes and failures, which will benefit future activity on this project and on future projects. Which tool and technique arc they using? A. Product documentation inspection B. Contract process review C. Performance measurement review D. Procurement audit

767


You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope as the glitch changed the characteristics of the product. Which of the following is true? A. Changes to product scope are reflected in the project scope. B. Changes to product scope are reflected in the integrated change control plan. C. Changes to product scope are a result of changes to the product description. D. Changes to product scope are a result of corrective action.

567


Which of the following is true regarding schedule variances? A. They impact scope, which impacts the schedule B. They sometimes impact the schedule C. They always impact the schedule D. They never impact the schedule

614






You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.

595


All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance

560


All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT

559


Project managers spend what percentage of their prime communicating? A. 90 B. 85 C. 75 D. 50

520


All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.

545


What are the different types of software risks?

526


The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

1247


You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You’re heading up a project to promote a new line of souvenirs to be sold at the shows. You need to gather the inputs to write the scope statement. You gather which of the following? A. Project charter, product description, assumptions, and constraints B. Project charter, product analysis, and cost benefit analysis C. Product description, product analysis, and project charter D. Product description, assumptions, constraints, and product analysis

682


You've reached a stale of independence where you're able to express yourself and perform at your peak level of performance. Being the best you can be is the motivator that drives you. Which of the following is true? A. This is an example of the Expectancy theory. B. You've reached self-actualization in Maslow's Hierarchy. C. This is an example of the Hygiene theory. D. You've reached the highest level of the Achievement theory.

681


You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management

675