How do we calculate the weight of aggregates, sand and
cement M 25 design mixfor 1 cum
Answer / sjtbehera
. REQUIREMENTS
a) Specified minimum strength = 20 N/Sq mm
b) Durability requirements
i) Exposure Moderate
ii) Minimum Cement Content = 300 Kgs/cum
c) Cement
(Refer Table No. 5 of IS:456-2000)
i) Make Chetak (Birla)
ii) Type OPC
iii) Grade 43
d) Workability
i) compacting factor = 0.7
e) Degree of quality control Good
2. TEST DATA FOR MATERIALS SUPPLIED
a) CEMENT
i) Specific gravity = 3.05
ii) Avg. comp. strength 7 days = 46.5 more than 33.0 OK
28 days = 55.0 more than 43.0 OK
b) COARSE AGGREGATE
i) 20mm Graded
Type Crushed stone aggregate
Specific gravity = 2.68
Water absorption = 1.46
Free (surface) moisture = 0
c) FINE AGGREGATE (Coarse sand)
i) Type Natural (Ghaggar)
Specific gravity = 2.6
Water absorption = 0.5
Free (surface) moisture = 1.4
3. TARGET MEAN STRENGTH (TMS)
a) Statistical constant K = 1.65
b) Standard deviation S = 4.6
Thus, TMS = 27.59 N/Sqmm
4. SELECTION OF W/C RATIO
a) As required for TMS = 0.5
b) As required for ‘Moderate’ Exposure = 0.55
Assume W/c ratio of 0.5
5. DETERMINATION OF WATER & SAND CONTENT
For W/C = 0.6
C.F. = 0.8
Max. Agg. Size of 20 mm
a) Water content = 186 Kg/cum
b) Sand as percentage of total aggregate by absolute
volume = 35 %
Thus,
Net water content = 180.42 Kg/cum
Net sand percentage = 33 %
6. DETERMINATION OF CEMENT CONTENT
W/c ratio = 0.5
Water content = 180.42 Kg/cum
Thus, Cement content = 360.84 Kg/cum Adequate for moderate
exposure Say 360 Kg/cum
7. DETERMINATION OF COARSE AND FINE AGGREGATE CONTENT
Assume entrapped air as 2 %
Thus,
0.98 cum = [180.42+360/3.05 + {1/0.33}*{fa/2.6}]/1000
& 0.98 cum = [180.42+360/3.05 + {1/0.67}*{Ca/2.68}]/1000
Hence,
fa = 584 Kg/cum
Ca = 1223.8 Kg/cum
The final mix proportions of M-20 grade of concrete become:-
Note: 1 The above recommended mix design must be verified,
by actual cube tests.
2 The mix design is based on the quality and grading of
the materials actually supplied, by the client.
Any variation in quality and gradation will result in
changes in the mix design
| Is This Answer Correct ? | 3 Yes | 1 No |
Describe the advantages and disadvantages of using plastic and timber fenders?
how to calculate freeboard in under ground water tank and technical details
How many square meter can mason layout chb per hour
How do you maintain water pressure?
How to calculate steel for beam slab and column
Steel requirement in kg of 6" thk slab Total qty 32.64 m3 Beam / column qty 35.39 m3
How to calculate the sand and aggregate in concrete
what will happen if we pass electric current through rebars of RCC Slab(is there any strength reduction of concrete during this)??????????
2 Answers Precast, SPC Systems,
what quantities of work done in terms of sq.mts/day/ of 8hrs for each varpenter (shuttering) and Steel fitter in terms of Tonnes. For slabs, Columns etc.?
reinforcement slab, beam and column formulas?
how to identify different types of soils in field?
I want to know how much the lapping length for the pilecap reinforcement.. we r using single pile cap which is 24mby54m and 2.5m depth.. total 91piles are supporting the pile cap.. how to do a steel reinforcement??
Civil Engineering (5086)
Mechanical Engineering (4456)
Electrical Engineering (16639)
Electronics Communications (3918)
Chemical Engineering (1095)
Aeronautical Engineering (239)
Bio Engineering (96)
Metallurgy (361)
Industrial Engineering (259)
Instrumentation (3014)
Automobile Engineering (332)
Mechatronics Engineering (97)
Marine Engineering (124)
Power Plant Engineering (172)
Textile Engineering (575)
Production Engineering (25)
Satellite Systems Engineering (106)
Engineering AllOther (1379)